UAT 312 Mission Planning, Autonomous Operations and Beyond Visual Line of Sight

Worksheet 1 A mission concept pack

Analysis activity 4 hAssesses CLO1

Objective

Analyse a hypothetical 2 km canal survey, define the three area layers, compute survey lines and energy budget, and list assumptions still to check

Equipment and materials

  • Worksheet B01 from the drone knowledge hub
  • Practice map
  • Calculator or computer with Python and module 1 example code (m1_lesson_code.py)
  • Energy values given by the instructor

Safety

  • Classroom desk work; no flying
  • The pack is an exercise, not an authorised flight plan

Steps

  1. Write a one-page brief with question, recipient, timing and team roles
  2. Sketch flight geography, contingency volume and ground risk buffer with reasons
  3. Compute GSD, line spacing and flight time
  4. Check the energy budget with the instructor's values, including wind
  5. Build an assumption register with items to check, data owners and HOLD conditions

Record of results

Table 1 The three layers of the operational area
LayerWidth or distance set (m)Reason or source of the distanceWhat lies in this layer (roads, houses, people)
Table 2 Survey-line and energy-budget calculations
QuantityFormula usedValues substitutedResult with unit
Table 3 Assumption register
AssumptionHow to check itData ownerCondition that triggers HOLD

Questions

  1. If the brief requires a GSD no coarser than 3 cm per pixel, how does the height from the formula differ from the height you would actually fly, and why?

  2. Compare your calm-air flight time with the time in a wind along the canal. Why does the wind make the flight longer even though there is both a headwind and a tailwind?

  3. From your group's energy budget, can the mission be flown in one sortie? If not, how would you split it and what would you build into the plan?

  4. Which assumption in Table 3 would be most dangerous if it were wrong, and how could your group confirm it before the flight day?

Check before you hand in

What to hand in

  • One-page brief
  • Three-layer area map
  • Survey-line and energy calculations
  • Assumption register

CLO1 Plan automated missions systematically. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack