UAT 366 Indoor Autonomous and Multi-Unmanned Aircraft Systems
Worksheet 5 A multi-drone stock-counting operations plan
Objective
Plan a multi-drone stock count with balanced jobs, no conflicts with forklifts or people, a risk assessment and a whole-system test against the plan
Equipment and materials
- Lab laid out as mock warehouse aisles
- Drones and systems from worksheets 1–4
- Stopwatch
- Python and the module 5 example code
Safety
- Set no-fly zones, fire exits and emergency landing spots before testing
- No people in the flight zone during tests
- Test position-loss, low-battery and link-loss behaviour in SITL before real flight
- One pilot per drone and an emergency stop
Steps
- Time the scan per aisle and split jobs among two or three drones with Example 1
- Build a mock forklift schedule, check it with Example 2 and adjust until nothing overlaps
- Draw the zone plan with charging pads, fire exits and no-fly areas
- Write the risk assessment and behaviour on position loss, low battery and link loss
- Test the whole system in the lab and record actual versus planned completion time
Record of results
| Drone | Aisles assigned | Planned time (min) | Actual finish (min) | Difference and cause |
|---|---|---|---|---|
| Aisle | Drone slot (min) | Forklift slot (min) | Buffer (min) | Result (conflict or ok) | Fix |
|---|---|---|---|---|---|
| Hazard | Likelihood | Severity | Control measure | Drone behaviour set |
|---|---|---|---|---|
Questions
From Table 1, how far is the LPT finish time from the lower bound and from Graham's bound, and why use LPT in a warehouse with hundreds of aisles instead of trying every assignment?
In Table 2, which jobs overlapped, how did the group fix it, and why is a buffer needed even when slots do not exactly overlap?
Why should the behaviour on loss of position indoors be to land immediately rather than return to base?
How far was the actual finish time from the plan, and why? How should the plan be adjusted next time?
Before using the system in a real factory, what must the team do about indoor flight requirements, as summarised in the lesson?
Check before you hand in
What to hand in
- LPT job split
- Conflict-free drone and forklift schedule
- Zone plan
- Risk assessment
- Whole-system test results against the plan