UAT 458 Indoor Autonomous UAS and Navigation Technology

Worksheet 5 Plan and test an indoor inspection mission

Lab 6 hAssesses CLO3, CLO5

Objective

Plan a route from the map, turn it into a mission, configure safety settings and test in stages with test cards and statistics, as the end-of-term mini-project

Equipment and materials

  • Map tied to the plan from worksheet 3 and results from worksheet 4
  • Computer with SITL and the example code
  • Training drone with a tested indoor position source and avoidance
  • Netted test area or a permitted empty building

Safety

  • Test in order without skipping stages; real flights only under the instructor's supervision
  • Set failsafes to Land or Brake then Land and test them in SITL before real flight
  • Keep people from under the flight path; pilot, observer and area controller at their posts
  • Charge batteries only where permitted and never unattended

Steps

  1. Build a grid for the flight layer, inflate obstacles by aircraft size and stopping distance, and plan the route with Example 1
  2. Define at least 8 inspection points, convert them with Example 2 and check battery time
  3. Configure failsafes, fences and emergency switches, then test in SITL including position-source loss
  4. Write test cards for stages 1 to 6 with acceptance criteria and test in order
  5. Count passed flights in stage 6, compute the failure-rate upper bound with Example 3 and state the limits of the evidence
  6. Compile the mini-project report and prepare the demonstration

Record of results

Table 1 Inspection points and mission waypoints
PointN (m)E (m)Height (m)Latitude (7 decimals)Longitude (7 decimals)
Table 2 Failsafe tests in SITL
CaseSettingExpected actionResult in SITL (log no.)
Table 3 Test cards for stages 1 to 6
StageWhat is testedAcceptance criterionActual resultLog no.Pass or fail

Questions

  1. How much longer did inflating obstacles make your route, which gap was closed, and does the inflation agree with the avoidance stopping distance from Worksheet 4?

  2. How long does your mission take compared with the time allowed after the battery reserve? Which part takes most of the time, and what must you do if inspection points are added?

  3. How many stage 6 flights passed? What is the 95% upper bound on the failure rate, and how far can the group's safety claim go?

  4. Why can the maximum-altitude fence (FENCE_ALT_MAX) not guard the roof of a room lower than 10 m, and what did the group use instead?

  5. Why must latitude and longitude keep at least seven decimal places? With only five, roughly how far could a waypoint shift?

Check before you hand in

What to hand in

  • Route, inspection points and mission file
  • Safety settings and SITL test results
  • Completed test cards with log numbers
  • Mini-project report and demonstration

CLO3 Plan routes and test indoor autonomous missions step by step and safely, using measurable acceptance criteria. CLO5 Apply sensor fusion, mapping, path planning and real-time localization to navigate unmanned aircraft indoors. (CLOs are a web-team draft; the course owner sets the final ones.)