UAT 301 Unmanned Aircraft Systems Technology

Worksheet 5 A system selection proposal

Analysis activity 4 hAssesses CLO2, CLO3

Objective

Select a UAS for a mission using must requirements, weighted scoring, sensitivity testing and lifecycle cost

Equipment and materials

  • Real manufacturer documents from at least three suppliers
  • Python or a spreadsheet and the module 5 example code

Safety

  • Desk work only; no flying
  • State the source and date of every price and specification

Steps

  1. In class: choose a real mission in your province and write at least three measurable must requirements
  2. In class: find at least three options, including contracting a service and improving the current method, and screen them with the musts
  3. Self-study: score with weights and test sensitivity with Examples 1 and 2
  4. In class: compute annual cost and break-even with Example 3 including insurance, training and spare batteries
  5. Self-study: write a one-page proposal for managers in which every number can be traced, and prepare slides
  6. In class (week 15): present the proposal and answer questions

Record of results

Table 1 Must requirements and screening
OptionMust 1Must 2Must 3Pass?
Table 2 Weighted scores and sensitivity
CriterionWeightOption AOption BOption CEffect of weight ±0.10
Table 3 Lifecycle cost and break-even
Cost itemOwn (THB/yr)Contract (THB/yr)Improve current method (THB/yr)Source and date

Questions

  1. Did screening with must requirements remove an option that would have won on scores alone? Without screening first, what kind of proposal would management receive?

  2. Which weight change brought the first and second options closest, and what data should the team check further?

  3. In Example 3, if spare batteries add 30,000 THB a year to fixed costs, what does the break-even become, and at 12 missions a year should the province own or contract?

  4. For your group's mission, is a COTS or a custom-built system more suitable? Answer with the four questions from the lesson.

  5. If cost says contract but disaster work needs flights within a few hours, how should the proposal to management handle this?

Check before you hand in

What to hand in

  • Must requirements and screening results
  • Score table and sensitivity results
  • Lifecycle cost and break-even table
  • One-page proposal and slides

CLO2 Select UAS and payloads to fit missions. CLO3 Evaluate COTS versus custom-built systems. (CLOs are a web-team draft; the course owner sets the final ones.)