UAT 453 UAS for Infrastructure, Energy and Utility Inspection
Worksheet 7 A line inspection plan
Objective
Plan a distribution-line inspection that resolves the smallest required part at a safe distance, with time, batteries, flight sequence and coordination
Equipment and materials
- Map or satellite image of the line
- Lab zoom camera data
- Computer with Python and the module 7 example code
- Flight plan form
Safety
- Desk planning; no flights near real lines
- Chosen take-off points must be clear of lines and safely accessible
- Real flights always need utility coordination and CAAT approval first
Steps
- Take the assigned line and measure it on the map
- Agree the smallest part to be seen
- Compute stand-off at several focal lengths with Example 1
- Choose safe, accessible take-off points; compute time and batteries with Example 2
- Write a standard sequence for one tower and a file-naming scheme
- List the organisations to coordinate with before real flights
Record of results
| Focal length (mm) | Required GSD (mm) | Distance (m) | Meets the minimum clearance? |
|---|---|---|---|
| Line length (km) | Reach (km) | Take-off points | Minutes per point | Batteries per point | Total flying hours |
|---|---|---|---|---|---|
Questions
Which focal length did you choose, and why is flying closer for sharper images the wrong choice?
If the smallest part were 8 mm instead of 5 mm, what distance would the 50 mm zoom allow?
How does the computed flying time compare with a real working day, and what does the code not count?
Why have a standard tower sequence and record tower number and phase in the field?
Check before you hand in
What to hand in
- Line map with take-off points
- Focal length against stand-off table
- Time and battery calculation
- Tower sequence, file naming and coordination list