UAT 459 UAS, Internet of Things and Smart Warehouse Systems

Worksheet 4 Plan one night's routes and schedule

Lab 8 hAssesses CLO2

Objective

Plan routes and a schedule for the mock warehouse within safety and energy limits, and test-fly one aisle safely

Equipment and materials

  • Computer with the module 4 example code
  • The mock warehouse layout from worksheet 1
  • A small training drone with propeller guards, and a netted enclosure or training field
  • Spare batteries and fire-resistant bags or boxes for lithium batteries

Safety

  • Fly only in a netted enclosure or training field under instructor supervision, in visual line of sight, with people kept clear
  • Any flight outside an enclosure must meet the CAAT notification's conditions
  • Check batteries and propellers before every flight and store lithium batteries in fire-resistant bags or boxes

Steps

  1. Set route constraints, including side clearance, ceiling limit, geofence and no-entry aisles, and show the clearance calculation
  2. Compute scan times and check energy for every aisle with Example 1, keeping at least 60 s of margin
  3. Generate 12 unread locations, route them with Example 2 and compare with a hand-planned order
  4. Schedule two drones with Example 3, with aisle A02 unlocking only after minute 30
  5. Test-fly one aisle in the enclosure and compare actual time with the calculation

Record of results

Table 1 Route constraints and clearance calculation
ConstraintValueUnitSource or calculation
Table 2 Time and energy per sortie
Aisle or sortieScan time (s)Transit (s)Total (s)Margin to 900 s (s)Actual test-flight time (s)
Table 3 Re-flight route and two-drone schedule
DroneSortie orderStart (min)End (min)Notes (such as A02 unlocking after minute 30)

Questions

  1. With at least 60 s of energy margin, which sorties must be split further, compared with Example 1 which had no margin rule, and why is a margin of a few seconds not usable in practice?

  2. How much shorter is the nearest neighbour plus 2-opt route than the order the group planned by hand? If straight-line distances were used instead of detours through the cross-aisles, how would the time be wrong?

  3. How did the condition that A02 unlocks only after minute 30 change the schedule and finishing time? Compared with the lower bound and the 22:00 to 05:00 window, how often can the warehouse be scanned?

  4. How far was the actual test-flight time from the calculation? What does that say about the energy margin to use, and why must collision prevention never replace routes planned with clearance?

Check before you hand in

What to hand in

  • Constraint table and clearance calculation
  • Time and energy per sortie
  • Re-flight route and two-drone schedule
  • Test-flight log compared with the plan

CLO2 Design drone inventory-counting and stock-inspection missions, including rack localization and indoor route planning. (CLOs are a web-team draft; the course owner sets the final ones.)