UAT 460 UAS for Public Safety, Search and Rescue, and Emergency Management
Worksheet 15 The handover package for the Phuwari case
Objective
Write an information-requirements table, rank findings, set a screening threshold, and prepare and present a two-copy handover package
Equipment and materials
- The instructor's list of twelve findings and a set of labelled image tiles
- Computer with Python, GIS software and GDAL
- Products of Worksheets 12 and 13 (polygon, orthomosaic, damage-grade table)
- Computer with Python and the example code at /downloads/uat-460/
Safety
- This is desk work; use assumed data only and never enter real personal data
- Do not upload group data to a public service, and remove location information from the public copy
- Any CAP message created must have the status Exercise and must not be sent as a real warning
Steps
- Write a five-row information-requirements table for the provincial director stating decision, essential information, product, source and deadline
- Compute S for the twelve findings, change two confidences, then write the list of findings to confirm by flying
- Run the detector on the labelled tiles, choose a threshold from reviewers and time, then report precision, recall and the number missed
- Compute the sizes and transfer times of the products, create GeoJSON and COG files, and check they open in GIS software
- Make two packages with a manifest, complete metadata and checksums, then give a three-minute briefing to the "director"
Record of results
| Decision | Essential information | Product | Source | Deadline |
|---|---|---|---|---|
| Finding | n, h, c | S = cn/h | Rank | Confirm by flying? |
|---|---|---|---|---|
| Item | Value | Unit | Notes |
|---|---|---|---|
Questions
Which finding moved most when confidence was included, and how did the top five change when your group changed two confidences?
What precision and recall did your threshold give, how many were missed, and how must the misses be told to the decision-maker?
Why send the polygon and overview before the full orthomosaic, and how long does a 500 MB file take over a 2.8 Mbit/s link?
How do the operational and public packages differ, why do they need a version number and checksum, and why does the drone team not issue the warning itself?
Check before you hand in
What to hand in
- Five-row information-requirements table
- Table of index S and the list of findings to confirm by flying
- Report of precision, recall and the chosen threshold
- Operational and public handover packages with manifest, and the three-minute briefing slides