UAT 497 Co-operative Education in Unmanned Aircraft Systems and Automation Technology
Worksheet 4 Prove the result and hand over
Objective
Take part in the supervision visit and mid-placement evaluation, pilot the new method on real jobs, measure against the baseline, assess value and sensitivity, and hand over through management of change
Equipment and materials
- At least four real jobs approved by the mentor
- The same timing form as the baseline
- Python and module 4 example code
- The company's management-of-change form
- The programme's mid-placement evaluation form (six competencies, scale 1–5)
Safety
- Pilot the new method only with the mentor's approval and without removing existing safety steps
- Flights follow CAAT conditions and company manuals
- Use real company data only where permitted
Steps
- At least one week before the week 8 visit, send the progress report to the academic supervisor and self-rate on the mentor's form; if the mid-placement result is low, write an improvement plan as in Example 2 signed by all three parties
- Pilot on at least four real jobs, timing as for the baseline and counting report corrections
- Compute savings, NPV and payback with Example 1
- Test sensitivity: halve jobs per year and check whether NPV stays positive
- Write the new SOP and submit it through management of change
- Train the owner, have them do one report alone with the new method and record the result
Record of results
| Job | Report time | Other steps total | Total time | Times sent back for correction |
|---|---|---|---|---|
| Item | Base case | Case with jobs per year halved | Unit |
|---|---|---|---|
| Competency | Mentor | Lecturer | My self-rating | In the improvement plan? |
|---|---|---|---|---|
Questions
How many hours and what percentage did each step's pilot average change against the baseline, how much did the total time per job fall, did every job meet the target, and did the number of times sent back for correction go up?
From Table 2, what are the project's NPV and payback, is the time saved real cash for the company, and which results that cannot be measured in money should be written separately?
When jobs per year are halved, how do NPV and payback change, what is the minimum number of jobs per year for the project to stay worthwhile, and is the result robust to changing assumptions?
Under the course's low mid-placement rule, which competencies must enter the improvement plan, what must the plan contain, and why must the re-evaluation check every indicator in the plan?
Why must the owner do one report alone without help, and why submit the SOP through management of change and keep the code in the company repository instead of editing the shared template yourself?
Check before you hand in
What to hand in
- Progress report, mid-placement evaluations and improvement plan (if results are low)
- Pilot results against baseline
- Economic and sensitivity results
- New SOP with submission record
- Handover result record