UAT 302 UAS Installation and System Integration

Worksheet 1 An integration plan for the training drone

Lab 12 hAssesses CLO3, CLO1

Objective

Write the interface register, find the installation order and critical path, allocate ports and set pass criteria for each step

Equipment and materials

  • Training drone and parts list
  • Flight controller hardware page from ArduPilot or PX4 docs
  • Computer with Python and the module 1 example code
  • Calibrated torque driver, and a coin or light hammer for tap testing

Safety

  • Desk work and frame assembly only; no battery connected, no flying
  • Tighten screws with the torque driver to the frame manual's values; never over-tighten, as the thread or the carbon around the hole may be damaged, and check carbon parts for cracks or frayed edges before handling

Steps

  1. Write the full interface register for the training drone
  2. Draw the dependency graph; use Example 1 to find the task order and critical path
  3. Read the flight controller hardware page; allocate ports with Example 2
  4. Set pass criteria for each step, such as GNSS 3D fix with HDOP below the agreed value
  5. Inspect the frame parts, assemble in the manual's order, log every joint's torque and check the log with Example 3
  6. Have another team review the register and plan; fix their findings

Record of results

Table 1 Interface register of the training drone (with port and I2C allocation)
From device to devicePort (SERIALn), connector or I2C addressSignal type, protocol and data rateSignal voltage level (V)Current drawn (A)Parameters to set, and Example 2 check result
Part 2 Installation order, critical path and pass criterion for each step (attach the Example 1 output)
Table 3 Airframe assembly torque log
Joint (screw size)Torque from the frame manual (N·m)Torque applied (N·m)Tool used and last calibration dateExample 3 result (pass, or redo and why)

Questions

  1. From your Example 1 output, which tasks are on the critical path, and how many hours can each other task slip without delaying the whole job? With two people, who should start which task first?

  2. If Example 2 finds the companion computer on the GPS1 port, how many things are wrong, what are they, and how do you fix them? Refer to your Table 1.

  3. In Table 3, if a joint shows the right torque but the driver is out of calibration, why must it still be redone? What must be checked on an over-torqued joint before refitting it?

  4. Which of your pass criteria is the most clearly measurable, and which cannot really be measured yet? If you had no step criteria and tested only once at the end, what would happen when a fault appeared?

Check before you hand in

What to hand in

  • Interface register
  • Dependency graph and task order
  • Checked port allocation table
  • Per-step pass criteria and peer-review notes
  • Assembly torque log with check results

CLO3 Document configurations and interface registers. CLO1 Install and interface flight controllers, sensors and power. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack