UAT 302 UAS Installation and System Integration

Worksheet 3 A harness that can be checked

Lab 12 hAssesses CLO1, CLO3

Objective

Budget every rail's current, write and check the wire list, and power up safely for the first time

Equipment and materials

  • Training drone and device specifications
  • Wire code labels
  • Multimeter
  • Bench supply or current limiter for first power-up
  • Python and the module 3 example code

Safety

  • Propellers off throughout
  • Test continuity and shorts before every power-up
  • First power-up only through a current limiter
  • Disconnect the battery before changing wiring

Steps

  1. Budget every rail with Example 1 from real specifications
  2. Write the full wire list; label the real wires
  3. Check the list with Example 2; fix wires with failing voltage or mismatched signal levels
  4. Test continuity and shorts, then power up first through a current limiter
  5. With propellers removed, calibrate PWM ESCs (skip for DShot), run the motor test and check order and direction with Example 3
  6. Measure end voltages with the companion computer at full load; record them

Record of results

Table 1 Current budget of each rail
RailRating (A)Devices and peak current from datasheets (A)Total (A)Utilisation (%)Passes 80% rule? What was fixed
Table 2 Wire list with checks and end voltages
Wire ID, from, toSignal type, AWG and round-trip length (m)Current (A) or logic level at each end (V)Calculated end voltage (V) or logic-level checkEnd voltage measured at full load (V)Pass or fail
Table 3 Motor test results (propellers off)
Button pressedMotor number, expected position and directionPosition that spun and direction seen from aboveExample 3 result and fix

Questions

  1. Which rail in Table 1 has the highest utilisation? If it looks fine on the bench, why might it still reset in the air, and what are the ways to fix it?

  2. In Table 2, how much of the voltage drop on the companion computer's supply comes from the wire and how much from the connectors? How much would the end voltage change if one connector were removed?

  3. Does your measured end voltage differ from the calculated one? If it is lower, what causes might the calculation have left out?

  4. If buttons C and D spin each other's motors, do you fix the signal wires or the motor wires? If a motor is in the right place but turns the wrong way, how do you fix it, and what would happen if the drone flew like that?

  5. Why must the first power-up go through a current limiter with the propellers off, even after continuity testing?

Check before you hand in

What to hand in

  • Current budget table
  • Wire list with check results
  • Pre-power test record
  • End-voltage table
  • Motor test record (order and direction)

CLO1 Install and interface flight controllers, sensors and power. CLO3 Document configurations and interface registers. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack