UAT 316 Technology Project Management, Innovation and Entrepreneurship

Worksheet 4 Analysing cost options

Analysis activity 4 hAssesses CLO3

Objective

Compare options by TCO, break-even and NPV, test assumptions and draft TOR acceptance criteria

Equipment and materials

  • Worksheet E02 in the knowledge unit on lifecycle cost and acceptance
  • Spreadsheet or Python and the module 4 example code

Safety

  • Desk work only; no flying

Steps

  1. Compute TCO for the two options in worksheet E02
  2. Increase the in-house option's maintenance by 30% and find the new break-even
  3. Compute NPV at 6% with cash flow of 250,000 baht a year and find the minimum cash flow for a non-negative NPV
  4. List at least five costs the lesson example does not count
  5. Draft three TOR acceptance criteria stating the deliverable, test method and evidence the contractor must submit

Record of results

Table 1 Three-year TCO and break-even before and after a 30% maintenance increase
CaseJobs per yearIn-house (baht)Service (baht)Cheaper optionBreak-even (jobs per year)
Table 2 NPV at a 6% discount rate as cash flow changes
Cash flow per year (baht)NPV at 6% (baht)Simple payback (years)Conclusion
Table 3 TOR acceptance criteria
DeliverableAcceptance criterion (number)Test methodEvidence the contractor submits

Questions

  1. After the 30% maintenance increase, where does the break-even move? At 24 jobs a year is in-house still better, and in what range of jobs per year could the recommendation easily flip?

  2. Is NPV still positive at 250,000 baht a year, and how far is the minimum cash flow you found from the expected 350,000 baht? What does that margin say about the project's risk?

  3. Of the at least five costs the example leaves out, which would move the break-even most, and in which direction?

  4. Why must cost be divided by accepted jobs rather than all jobs, and how do your TOR acceptance criteria make the two options fairly comparable?

Check before you hand in

What to hand in

  • TCO and break-even before and after the change
  • NPV and minimum cash flow
  • List of missing costs
  • Three acceptance criteria

CLO3 Assess cost, risk and feasibility. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack