UAT 362 Unmanned Aircraft Systems Technology for Industrial, Energy and Infrastructure Applications
Worksheet 5 Risk plan and inspection report
Objective
Assess flight and asset risk, and turn defects into recommendations and work orders the operator can use
Equipment and materials
- Defects collected in worksheets 2–4
- Python and the module 5 example code
- Spreadsheet or CMMS import template
- Lab notebook
Safety
- Desk work and presentation only; no flying
Steps
- Identify at least six hazards for an inspection flight on site and assess them with Example 1 before and after mitigation
- Score PoF and CoF for each defect with reasons and rank them with Example 2
- Write one report entry per defect with all required information
- Build a table importable into a CMMS or the operator's spreadsheet, with an image manifest
- Present to the asset manager (the instructor) and adjust the ranking with added consequence information
Record of results
| Code and hazard | Probability-severity before | Score and band before | Mitigation | Probability-severity after | Score and band after |
|---|---|---|---|---|---|
| Defect and asset ID | Location | PoF and reason | CoF and reason | Risk and level | Due (days) |
|---|---|---|---|---|---|
| File name | Defect code | SHA-256 | Original or working copy |
|---|---|---|---|
Questions
After mitigation, which hazards in Table 1 are still medium or high? May your group fly, and what more is needed?
In Table 2, does the defect that looks worst in the images rank first? Use PoF and CoF to explain why consequences matter as much as visible severity.
After your presentation the asset manager gives extra consequence information that changes one defect's CoF. How do the ranking and due date change?
What does the SHA-256 manifest in Table 3 prove, and what does it not prove?
Why must the job be re-inspected after repair before the work order is closed, and which step of the asset management loop does that link back to?
Check before you hand in
What to hand in
- Flight risk register
- Ranked defect table
- Inspection report
- Work order table with manifest