Module 10/15 · Weeks 10 · 9 h

Asset-condition analysis and maintenance reporting

UAT 453 UAS for Infrastructure, Energy and Utility Inspection

About 80 minDraft, awaiting reviewLast updated 30 September 2026

Lesson

By the end of this module you will be able to

  1. Prioritise findings by severity and consequence and set repair time frames
  2. Analyse trends across several inspections to predict when a threshold will be reached
  3. Write maintenance work orders that technicians can act on immediately
  4. Link drone inspection results with the owner's asset management system

Prerequisites: Module 9 Solar farms, wind turbines and pipelines

Why this matters

Thousands of thermal images are worth nothing unless they become repairs done at the right time. Technicians must know where to go, what to do, what equipment to bring and how urgent it is. Managers must know where to spend budget first and which assets are deteriorating. This module closes the loop from data to maintenance.

Prioritising findings

Score each item by severity (from technical criteria such as NETA ΔT) and consequence if it fails (such as customers affected or safety), then use the product to set the repair time frame.

Example 1 Five items from this inspection

The time frames per score are the company’s assumed rules.

findings = [   # (code, severity 1-3, consequence 1-3)
    ("F01 tower 31 clamp dT 22 C", 3, 3), ("F02 60 PV modules bypass diode", 2, 2),
    ("F03 blade 2 leading-edge erosion", 2, 3), ("F04 tower 23 jumper dT 9 C", 2, 3),
    ("F05 pipeline marker missing", 1, 1),
]
deadline = {9: "within 24 h", 6: "within 1 month", 4: "within 3 months", 3: "next planned outage", 2: "next inspection", 1: "next inspection"}
for code, sev, con in sorted(findings, key=lambda f: -f[1] * f[2]):
    print(f"{code:<34} score {sev * con}  -> {deadline[sev * con]}")
F01 tower 31 clamp dT 22 C         score 9  -> within 24 h
F03 blade 2 leading-edge erosion   score 6  -> within 1 month
F04 tower 23 jumper dT 9 C         score 6  -> within 1 month
F02 60 PV modules bypass diode     score 4  -> within 3 months
F05 pipeline marker missing        score 1  -> next inspection

The tower 31 connection (ΔT 22 °C) on a line feeding a wide area scores highest and must be repaired within 24 hours. The eroded blade edge and the tower 23 connection fall into the within-a-month group. The modules with failed diodes lose revenue every day but do not affect safety, so they are repaired within three months. The owner must approve such criteria before use.

A 3 by 3 grid with severity on the vertical axis and consequence on the horizontal axis. Cells show scores 1 to 9 in green, yellow and pink. F01 is in the score-9 cell, F03 and F04 in a score-6 cell, F02 in the score-4 cell and F05 in the score-1 cell
Figure 1 Priority matrix of findings

A great advantage of drones is frequent, low-cost repeat inspection. With several inspections of the same asset, a trend line helps predict when it will reach a threshold, so repairs can be planned before failure rather than after.

Example 2 A connection whose ΔT rises each time

Inspected every 6 months at similar load.

months = [0, 6, 12]                        # survey time (months)
dts = [3.0, 6.0, 10.0]                     # ΔT of the same connector (°C) at similar load
n = len(months)
mx, my = sum(months) / n, sum(dts) / n
slope = sum((x - mx) * (y - my) for x, y in zip(months, dts)) / sum((x - mx) ** 2 for x in months)
inter = my - slope * mx
print(f"trend {slope:.3f} C per month")
print(f"reaches 15 C at about month {(15 - inter) / slope:.1f}")
trend 0.583 C per month
reaches 15 C at about month 20.9

ΔT rises by about 0.58 °C per month. If this continues, it will reach 15 °C (the immediate-repair criterion) around month 21 from the first inspection, so the repair should be scheduled in a planned outage before then. The limits are that there are only three data points, and connection degradation often accelerates when hot, so a linear trend may overestimate the time remaining; inspect more often as the threshold approaches.

Chart of ΔT by month. Three blue points at months 0, 6 and 12 have values 3, 6 and 10 degrees. A dashed purple trend line continues until it meets a dashed pink line at 15 degrees around month 21
Figure 2 ΔT trend of a connector over three surveys

Maintenance work orders

A good work order lets technicians arrive and work immediately.

  • Asset code and location, such as 115 kV line, tower 31, phase A, with coordinates
  • Finding: thermal and zoom images, ΔT, load at measurement, and date and time
  • Action: for example inspect and re-torque the connection, or replace the clamp
  • Urgency and time frame from the priority matrix
  • Safety requirements, such as an outage or a bucket truck
  • Verification: re-image thermally after repair

Linking with asset management

Energy companies usually have an asset management or maintenance system holding each asset’s history. Drone inspection results should enter this system under the same asset codes, to show continuous history, measure repair outcomes and adjust intervals by risk as in module 6. The loop is inspect → analyse → repair → verify → adjust the plan.

Module lab

Lab: from findings to work orders

  1. Gather the findings from modules 8 and 9, score severity and consequence, and rank them with the code in Example 1
  2. Choose an item with several inspections (or data your lecturer provides) and analyse its trend with the code in Example 2
  3. Write two work orders for the most urgent items, covering every heading
  4. Design a data table for the asset management system with the asset code as the key column
  5. Present a three-month maintenance plan to a classmate playing the manager

Common mistakes

Watch out

  • Ranking by severity alone without considering consequence
  • Treating a linear trend from few points as a firm schedule
  • Comparing ΔT across inspections at very different loads
  • Work orders without location or safety requirements, so technicians must come back to ask
  • Not verifying after repair, so nobody knows whether it worked

Summary

  • Rank findings with and owner-approved time frames
  • Trends across inspections predict the time to threshold , with care over few data points and accelerating degradation
  • Work orders need location, finding, action, urgency, safety requirements and verification
  • Feed results into the asset management system under the same codes, closing the loop of inspect, analyse, repair, verify and adjust

Check your understanding

  1. Severity 3 and consequence 2 give what score?
  2. ΔT of 4, 7 and 10 °C at months 0, 6 and 12 gives what trend per month?
  3. From question 2, in which month is 15 °C reached?
  4. Why might a linear trend overestimate the time remaining?
  5. Why must work orders include safety requirements?
Answers
  1. °C per month
  2. months
  3. Connection degradation often accelerates when hot rather than rising linearly
  4. Electrical work may need an outage or special equipment that technicians must prepare before arriving

Key formulas

Priority score
Linear trend
Time to threshold

Key references

  1. InterNational Electrical Testing Association. (2003). ANSI/NETA ATS-2003 Standard for acceptance testing specifications for electrical power equipment and systems (Table 100.18, Thermographic survey suggested actions based on temperature rise). link
  2. International Electrotechnical Commission. (2017). Photovoltaic (PV) systems – Requirements for testing, documentation and maintenance – Part 3: Photovoltaic modules and plants – Outdoor infrared thermography (IEC TS 62446-3:2017). link
  3. Barnhart, R. K., Marshall, D. M., & Shappee, E. (Eds.). (2021). Introduction to unmanned aircraft systems (3rd ed.). CRC Press. link
  4. NIST/SEMATECH. e-Handbook of statistical methods. National Institute of Standards and Technology. link

Further reading

Study the assigned knowledge units in advance, review media and take the module quiz

In class / field

Lab or field practice from worksheets with a safety checklist

Learning evidence: Checked worksheets and quiz results

Module quiz

This is a formative self-check, not a graded exam

Knowledge domain: Artificial intelligence and computer vision · Inspection, industry and surveillance · Surveying, mapping and geoinformatics