Asset-condition analysis and maintenance reporting
UAT 453 UAS for Infrastructure, Energy and Utility Inspection
Lesson
By the end of this module you will be able to
- Prioritise findings by severity and consequence and set repair time frames
- Analyse trends across several inspections to predict when a threshold will be reached
- Write maintenance work orders that technicians can act on immediately
- Link drone inspection results with the owner's asset management system
Why this matters
Thousands of thermal images are worth nothing unless they become repairs done at the right time. Technicians must know where to go, what to do, what equipment to bring and how urgent it is. Managers must know where to spend budget first and which assets are deteriorating. This module closes the loop from data to maintenance.
Prioritising findings
Score each item by severity (from technical criteria such as NETA ΔT) and consequence if it fails (such as customers affected or safety), then use the product to set the repair time frame.
Example 1 Five items from this inspection
The time frames per score are the company’s assumed rules.
findings = [ # (code, severity 1-3, consequence 1-3)
("F01 tower 31 clamp dT 22 C", 3, 3), ("F02 60 PV modules bypass diode", 2, 2),
("F03 blade 2 leading-edge erosion", 2, 3), ("F04 tower 23 jumper dT 9 C", 2, 3),
("F05 pipeline marker missing", 1, 1),
]
deadline = {9: "within 24 h", 6: "within 1 month", 4: "within 3 months", 3: "next planned outage", 2: "next inspection", 1: "next inspection"}
for code, sev, con in sorted(findings, key=lambda f: -f[1] * f[2]):
print(f"{code:<34} score {sev * con} -> {deadline[sev * con]}")
F01 tower 31 clamp dT 22 C score 9 -> within 24 h
F03 blade 2 leading-edge erosion score 6 -> within 1 month
F04 tower 23 jumper dT 9 C score 6 -> within 1 month
F02 60 PV modules bypass diode score 4 -> within 3 months
F05 pipeline marker missing score 1 -> next inspection
The tower 31 connection (ΔT 22 °C) on a line feeding a wide area scores highest and must be repaired within 24 hours. The eroded blade edge and the tower 23 connection fall into the within-a-month group. The modules with failed diodes lose revenue every day but do not affect safety, so they are repaired within three months. The owner must approve such criteria before use.
Trends across inspections
A great advantage of drones is frequent, low-cost repeat inspection. With several inspections of the same asset, a trend line helps predict when it will reach a threshold, so repairs can be planned before failure rather than after.
Example 2 A connection whose ΔT rises each time
Inspected every 6 months at similar load.
months = [0, 6, 12] # survey time (months)
dts = [3.0, 6.0, 10.0] # ΔT of the same connector (°C) at similar load
n = len(months)
mx, my = sum(months) / n, sum(dts) / n
slope = sum((x - mx) * (y - my) for x, y in zip(months, dts)) / sum((x - mx) ** 2 for x in months)
inter = my - slope * mx
print(f"trend {slope:.3f} C per month")
print(f"reaches 15 C at about month {(15 - inter) / slope:.1f}")
trend 0.583 C per month
reaches 15 C at about month 20.9
ΔT rises by about 0.58 °C per month. If this continues, it will reach 15 °C (the immediate-repair criterion) around month 21 from the first inspection, so the repair should be scheduled in a planned outage before then. The limits are that there are only three data points, and connection degradation often accelerates when hot, so a linear trend may overestimate the time remaining; inspect more often as the threshold approaches.
Maintenance work orders
A good work order lets technicians arrive and work immediately.
- Asset code and location, such as 115 kV line, tower 31, phase A, with coordinates
- Finding: thermal and zoom images, ΔT, load at measurement, and date and time
- Action: for example inspect and re-torque the connection, or replace the clamp
- Urgency and time frame from the priority matrix
- Safety requirements, such as an outage or a bucket truck
- Verification: re-image thermally after repair
Linking with asset management
Energy companies usually have an asset management or maintenance system holding each asset’s history. Drone inspection results should enter this system under the same asset codes, to show continuous history, measure repair outcomes and adjust intervals by risk as in module 6. The loop is inspect → analyse → repair → verify → adjust the plan.
Module lab
Lab: from findings to work orders
- Gather the findings from modules 8 and 9, score severity and consequence, and rank them with the code in Example 1
- Choose an item with several inspections (or data your lecturer provides) and analyse its trend with the code in Example 2
- Write two work orders for the most urgent items, covering every heading
- Design a data table for the asset management system with the asset code as the key column
- Present a three-month maintenance plan to a classmate playing the manager
Common mistakes
Watch out
- Ranking by severity alone without considering consequence
- Treating a linear trend from few points as a firm schedule
- Comparing ΔT across inspections at very different loads
- Work orders without location or safety requirements, so technicians must come back to ask
- Not verifying after repair, so nobody knows whether it worked
Summary
- Rank findings with and owner-approved time frames
- Trends across inspections predict the time to threshold , with care over few data points and accelerating degradation
- Work orders need location, finding, action, urgency, safety requirements and verification
- Feed results into the asset management system under the same codes, closing the loop of inspect, analyse, repair, verify and adjust
Check your understanding
- Severity 3 and consequence 2 give what score?
- ΔT of 4, 7 and 10 °C at months 0, 6 and 12 gives what trend per month?
- From question 2, in which month is 15 °C reached?
- Why might a linear trend overestimate the time remaining?
- Why must work orders include safety requirements?
Answers
- °C per month
- months
- Connection degradation often accelerates when hot rather than rising linearly
- Electrical work may need an outage or special equipment that technicians must prepare before arriving
Key formulas
| Priority score | |
| Linear trend | |
| Time to threshold |
Key references
- InterNational Electrical Testing Association. (2003). ANSI/NETA ATS-2003 Standard for acceptance testing specifications for electrical power equipment and systems (Table 100.18, Thermographic survey suggested actions based on temperature rise). link
- International Electrotechnical Commission. (2017). Photovoltaic (PV) systems – Requirements for testing, documentation and maintenance – Part 3: Photovoltaic modules and plants – Outdoor infrared thermography (IEC TS 62446-3:2017). link
- Barnhart, R. K., Marshall, D. M., & Shappee, E. (Eds.). (2021). Introduction to unmanned aircraft systems (3rd ed.). CRC Press. link
- NIST/SEMATECH. e-Handbook of statistical methods. National Institute of Standards and Technology. link
Further reading
Study the assigned knowledge units in advance, review media and take the module quiz
In class / field
Lab or field practice from worksheets with a safety checklist
Learning evidence: Checked worksheets and quiz results