UAT 453 UAS for Infrastructure, Energy and Utility Inspection
Worksheet 10 From findings to work orders
Objective
Prioritise findings, analyse trends, write maintenance work orders, design asset-management data and present a three-month plan
Equipment and materials
- Findings from worksheets 8 and 9
- Multi-round inspection data from the lecturer
- Computer with Python and the module 10 example code
- Work-order form
Safety
- Desk work; no flying
- Do not share university asset data outside the class
Steps
- Gather findings from modules 8 and 9; score severity and consequence
- Rank them with Example 1
- Pick an item with several rounds and analyse its trend with Example 2
- Write two complete work orders for the most urgent items
- Design the asset-management data table with the asset code as key
- Present a three-month maintenance plan to a classmate playing the manager
Record of results
| Finding code | Severity s (1-3) | Consequence c (1-3) | S = s × c | Repair time frame |
|---|---|---|---|---|
| Survey month | ΔT (°C) | Load at measurement (%) | Trend slope (°C/month) | Month expected to reach 15 °C |
|---|---|---|---|---|
Questions
Which item scored highest, and how would the order change if ranked by severity alone?
When does your trend say to repair, and what are the limits of a linear trend from three points?
Would your work order let technicians start work on arrival? Which headings were missing after a classmate read it?
Why must the asset code be the key column, and how does it close the inspect, analyse, repair, verify, adjust loop?
Check before you hand in
What to hand in
- Priority table
- Trend graph and conclusion
- Two work orders
- Data table and three-month plan slides