UAT 453 UAS for Infrastructure, Energy and Utility Inspection

Worksheet 6 A risk-based inspection plan

Field/workplace 4 hAssesses CLO4, CLO6

Objective

Survey campus energy assets, rank risk and set intervals, compute conductor sag and identify hazards with controls

Equipment and materials

  • Campus map or satellite image
  • Tape measure or laser range finder
  • Computer with Python
  • Example code at /downloads/uat-453/
  • Assumed conductor values from the lecturer

Safety

  • Ground survey only; no flying
  • Keep clear of lines, transformers and panels; never open panels or climb poles
  • Coordinate with facilities staff before entering areas

Steps

  1. Survey energy assets and list at least five
  2. Score likelihood and consequence with facilities staff
  3. Rank and set intervals with Example 1
  4. Measure or estimate one span
  5. Compute sag with Example 2 using the lecturer's assumed values
  6. List each asset's specific hazards and controls

Record of results

Table 1 Assets, risk scores and inspection intervals
Asset (photo no.)Likelihood P (1-5)Consequence C (1-5)R = P × CCurrent interval (months)Suggested interval (months)
Table 2 Conductor sag
Span L (m)Conductor weight w (N/m)Tension T (N)Sag s (m)Approx. mid-span conductor height (m)
Table 3 Specific hazards and controls
AssetSpecific hazardControlWho to coordinate with

Questions

  1. Which asset in Table 1 is riskiest, and how does the suggested interval differ from the current one?

  2. If the span doubles, how does sag change, and where would you measure tree clearance first?

  3. On a hot, high-load day, which way does your computed sag change, why, and how does that affect the flight plan?

  4. Why does a drone falling onto electrical equipment score a higher C than ordinary work? Give an example from your assets.

Check before you hand in

What to hand in

  • Asset list with photos
  • Risk and interval table
  • Sag calculation
  • Hazard and control table

CLO4 Explain UAS applications in energy and utilities. CLO6 Propose maintenance support from drone data. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack