UAT 457 UAS for Transportation and Autonomous Delivery
Worksheet 1 Mission requirements and aircraft selection
Objective
Write delivery mission requirements as checkable numbers, compare road and air time, select an aircraft with must-have criteria and weighted scores, and test an insulated box
Equipment and materials
- Online map and distance tool
- Specification sheets for at least three aircraft
- Foam box with ice pack and temperature logger
- Computer with Python and the example code at /downloads/uat-457/
Safety
- Mostly desk work; no flying
- Use ice packs as the maker directs; no dry ice in closed rooms
- Do not use real patient specimens to test the box
Steps
- Choose a route and write a requirements table covering all eight aspects as checkable numbers
- Find road distance, road time and straight-line distance, and compare times with Example 1
- Set must-have criteria and weights, agreed with the users (role-play)
- Score at least three aircraft with Example 2 and vary the weights to test sensitivity
- Leave the insulated box with a logger for 2 hours and compare temperatures with Example 3
Record of results
| Aspect | Question to answer | Requirement as a number with unit | How it will be checked |
|---|---|---|---|
| Destination | Road distance (km) and road time (min) | Straight-line distance (km) | Flight time (min) | Time saved (min and %) |
|---|---|---|---|---|
| Aircraft | Manufacturer round-trip range (km) | Passes must-have? | Score, first weights | Score, changed weights |
|---|---|---|---|---|
Questions
From Table 2, which destination gains most from a drone, and why? How would the result change if the fixed time per trip t0 grew a lot?
When the group changed the criterion weights, did the ranking of the aircraft that pass the must-have change? What would happen if failing aircraft were not removed first?
Does the box temperature logged over 2 hours agree with the holding time computed with Example 3? If not, what is the likely cause?
Which aspect in Table 1 was hardest to write as a number, and how did the group solve it? What permissions does the legal aspect of this route need?
Check before you hand in
What to hand in
- Mission requirements table
- Road versus air time table
- Scoring matrix with sensitivity results
- Logged temperature plot against calculation