UAT 457 UAS for Transportation and Autonomous Delivery

Worksheet 5 Fleet size and safety file

Analysis activity 6 hAssesses CLO3

Objective

Compute fleet size and maintenance intervals, assess ground risk with SORA, build an FMEA of the delivery system, and combine everything into the mini-project design file

Equipment and materials

  • Computer with Python and the example code at /downloads/uat-457/
  • Maps and public population-density data
  • SORA 2.5 tables and the latest CAAT notification
  • FMEA form

Safety

  • Desk work; no flying
  • Use area-level population data, not personal data
  • Label every assumed value clearly in the file

Steps

  1. Set daily demand and compute aircraft and battery numbers with Example 1 for normal demand and 50% more
  2. Build a three-month table of flight hours, maintenance and battery cycles with Example 2, staggered
  3. Draw the risk footprint of two corridors, find the highest density, and compute iGRC, GRC and SAIL with Example 3
  4. Build an FMEA of at least 8 items, propose measures and rescore with Example 4
  5. Combine modules 1–5 into a delivery-system design file for the week 8 presentation

Record of results

Table 1 Fleet size and battery numbers
CaseTrips per dayAircraft-hours per day (h)Aircraft (computed and rounded up)Average busy batteries LBatteries allocated
Table 2 SAIL for two corridor options
CorridorHighest footprint density (people/km²)iGRCMitigation and final GRCARCSAIL
Table 3 FMEA before and after measures
Failure modeS O DRPN beforeMeasureS O D afterRPN after

Questions

  1. Why must the number of aircraft be rounded up, and why allocate more batteries than the Little's law average?

  2. In the three-month maintenance table, what happens if all aircraft start together, and how did the group stagger them?

  3. Why is a corridor with a lower SAIL better, and what must be checked again once it is chosen?

  4. Does the group's FMEA have an item with a low RPN but high severity? How should it be ranked?

Check before you hand in

What to hand in

  • Fleet-size calculation
  • Maintenance and battery table
  • SAIL table for two corridors
  • FMEA tables before and after measures, and the delivery-system design file

CLO3 Manage the fleet and assess the safety of the delivery system against the law and risk-assessment methods. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack