UAT 460 UAS for Public Safety, Search and Rescue, and Emergency Management
Worksheet 16 Planning a mission to beat the commander's decision time
Objective
Analyse the situation as known, assumed and unknown information with constraint clocks, build a backward schedule from the decision time and find the critical path, rank information sources by their value, write six-field objectives and choose a set of objectives within the aircraft-minute budget
Equipment and materials
- High-rise fire scenario cards (handed out by the instructor, or a new incident card in the same format) and a form for the known, assumed and unknown table
- A computer with Python and the code of Examples 1 to 3 of Module 16
- Stopwatches for timing the planning and the field tasks
- A registered aircraft, charged batteries and a ground station for timing kit preparation and launch on the closed field
Safety
- Fly within visual line of sight in daylight under CAAT conditions, in an area closed to the public, never over people; the instructor checks the distance from uninvolved people, vehicles and buildings (50 m under the general conditions) before the flight points are set
- Check batteries before flight, charge them in a fire-resistant box away from people and keep an extinguisher at the launch point
- Everyone stays clear of the propellers and outside the flight path; fit propellers only when ready to fly and remove them for bench work on the aircraft
- The situation analysis, schedule and value-of-information work is desk work with assumed numbers, using no real incident or personal data
- Rest and drink water in the field, anyone tired or overheated does not take a duty, and hot batteries and airframes cool down before they are handled or charged
Steps
- Receive the scenario card at time T0 and start timing the planning at once, in teams of 4 to 5
- Write the known, assumed and unknown table with the source and age of every line, and at least five constraint clocks
- Split the work from receiving the request to reporting the result, add estimated durations, run the code of Example 1 to find the critical path, the float and the time left, then propose two options that add time
- Set the loss table of the decision, estimate the sensitivity and specificity of three sources, run the code of Example 2 to get the ranking and the decision threshold, then change the assumed values to see whether the ranking changes
- Write at least six objectives with all six fields, set the aircraft-minute costs, choose the best set for the budget the instructor sets with the code of Example 3 and check gate G1
- On the university's closed field, time the real kit-preparation and launch tasks, substitute the real times in Example 1, rerun it and report whether the critical path changed
- Submit mission file version 0, one page
Record of results
| Item | Known, assumed or unknown | Source | Age of information (min) | Related constraint clock |
|---|---|---|---|---|
| Task | Estimated duration (min) | Measured duration (min) | Earliest finish | Float (min) |
|---|---|---|---|---|
| Source or objective | Sensitivity / specificity or value | Minutes | EVSI or EVSI per minute | Chosen or dropped, with reason |
|---|---|---|---|---|
Questions
With the measured kit-preparation and launch times, did the critical path change, and how much time is left before the decision? Did your two time-saving options really help?
Why does speeding up a task off the critical path not help? Give an example from your Table 2.
Which source had the highest EVSI per minute, and why is a source that cannot change the decision worth zero? Did the ranking change when you changed the assumed values?
Did your chosen set differ from ranking by value per minute? How must a dropped objective be reported to the requester, and what was the G1 result?
Check before you hand in
What to hand in
- Known, assumed and unknown table with the constraint clocks
- Backward schedule, critical path, float and two options that add time, with the rerun using real times
- Value-of-information table (EVSI per minute) and decision threshold with the assumptions
- The chosen six-field objectives, the G1 result and the reasons for dropping the rest (mission file version 0)