UAT 474 Commercial Drone Media Production
Worksheet 2 Production plan and route test flight
Objective
Produce a full production plan covering location, legal paperwork, routes, schedule, batteries, crew, risk and budget, and test the routes
Equipment and materials
- Department small drone and simulator
- Stopwatch and anemometer
- Map or satellite image of the practice area
- Module 2 Examples 1 and 2
Safety
- Fly only in the university's designated practice area under instructor supervision, in daylight, within sight and no higher than 90 m
- Never fly over people and keep the required separation from people not involved; start in the simulator if not yet fluent
- Pre-flight, wind and battery checks as in UAT 471; charge batteries in a supervised, cool place
- Paperwork table uses assumed data; no real applications
Steps
- Survey the area: take-off points, obstacles, light, passers-by, with photos and coordinates
- Complete the legal paperwork table
- Write flight cards for at least 4 shots
- Test-fly two routes and time them
- Calculate packs per window and write a one-day call sheet
- Write the risk register and direct cost budget with contingency
Record of results
| Shot | Take-off point | Route and height (m) | Separation from people not involved, and abort trigger | Planned time (min) | Measured time (min) |
|---|---|---|---|---|---|
| Flight window | Planned or measured airtime (min) | Usable time per pack (min) | Packs needed |
|---|---|---|---|
| Category | Calculation | Amount (THB) |
|---|---|---|
Questions
Compare measured and planned times in Table 1. Which shot differs most and why? If the real time of each window were about 30% above plan, would the number of packs in Table 2 change?
Why must batteries be counted window by window rather than dividing the whole day's airtime once? Use your team's numbers to explain.
In your team's paperwork table, which items can the client or landowner not permit, and which items must have their expiry dates checked before the real flight?
Which budget category is the largest? Does that match what many people expect? If the spare weather day had to be used, how much would the total budget change?
Check before you hand in
What to hand in
- Recce notes
- Paperwork table
- Flight cards and measured times
- Call sheet
- Risk register and budget