UAT 493 Unmanned Aircraft Systems and Automation Technology Capstone Project I
Worksheet 5 Complete project proposal
Objective
Plan tests that verify every requirement, analyse risk with FMEA, write the methodology and development plan, and combine all deliverables into a proposal defended before a committee
Equipment and materials
- Worksheets 1–4
- Python and the module 5 example code
- Example 3 code for the schedule, critical path and budget
- Slide software
Safety
- Desk work and presentation; no flying
- Field tests in the proposal must state CAAT conditions and controls for high-severity failure modes
Steps
- Build an RVM for every requirement and check with Example 1 for 100% coverage and no activity without a requirement
- Plan tests following the V model and test ladder, stating each step's pass criteria before testing
- Do an FMEA of at least 10 failure modes following Example 2, rank them and state controls for every high-severity mode
- Write the methodology, build the WBS, a schedule with its critical path and a budget with contingency using Example 3, then assemble the proposal following Figure 2
- Present to the committee for 15 minutes, answer questions and revise as advised
Record of results
| Requirement ID | Verification activity | Method (inspection / analysis / demonstration / test) | Pass criterion set before testing | Level in the V model or test ladder |
|---|---|---|---|---|
| Failure mode | S | O | D | RPN (S × O × D) | Control |
|---|---|---|---|---|---|
| Work package (WBS) | Duration (weeks) | Depends on | Earliest finish (week) | Slack (weeks) |
|---|---|---|---|---|
Questions
Calculate the RVM coverage (requirements with a verification activity ÷ all requirements). Which requirements still have no verification activity, and which activities verify no requirement? What does each case tell the team?
Rank your team's failure modes by RPN and compare with ranking by severity. Which mode drops down when ranked by RPN, why is that dangerous, and where is its control in the test plan or work packages?
Which work packages are on the critical path, in which week does the project finish, and how many weeks of margin remain? If a work package with only 1 week of slack runs 2 weeks late, what happens to the finish and the margin?
What is the team's total budget before contingency? What contingency percentage was used, how many baht is it, and which FMEA failure mode is it tied to?
What did the committee ask that the first version of the proposal could not answer? Which part of the proposal did the team change, and how did it trace back to the requirements again?
Check before you hand in
What to hand in
- RVM and test plan
- FMEA table
- Methodology, WBS, schedule with critical path and budget
- Complete proposal and slides
- Revised version following committee advice