Test plan and proposal
UAT 493 Unmanned Aircraft Systems and Automation Technology Capstone Project I
Lesson
By the end of this module you will be able to
- Build a requirements verification matrix (RVM) and check test plan coverage
- Plan testing with the V model, from component tests to validation with users
- Analyse risk with FMEA and explain the move from RPN to Action Priority
- Write a methodology and build a development plan with a WBS, critical path and budget with contingency
- Assemble a project proposal in which every part traces back to the requirements
Why this matters
A good project proposal does not only say what will be built. It says how success will be proven and what could go wrong. Examiners will ask how a requirement will be tested and what happens if the camera fails in flight. A team that can answer from its own documents is ready to start building next semester.
The V model
Each layer on the left has a matching verification on the right. System requirements are verified by system tests, and user needs are confirmed by validation. The actual test sequence for a drone follows the ladder from SITL and HITL to field testing covered in UAT 322.
Requirements verification matrix (RVM)
The NASA Systems Engineering Handbook records verification in a requirements verification matrix that lists each requirement, its method, the test activity, the pass criterion and the result. The matrix is checked in two directions: every requirement must have a verification activity, and every activity must verify some requirement.
Example 1. Checking RVM coverage
requirements = ["R1", "R2", "R3", "R4", "R5a", "R5b", "R6", "R8"]
rvm = [ # (activity, requirements verified, method)
("T1 labelled image set", ["R1"], "Test"), ("T2 timed SITL round", ["R4"], "Test"),
("T3 GCP survey", ["R6"], "Test"), ("A1 storage estimate", ["R5a"], "Analysis"),
("D1 report walkthrough", ["R5b", "R8"], "Demonstration"), ("T4 motor noise log", [], "Test"),
]
covered = {r for _, reqs, _ in rvm for r in reqs}
missing = [r for r in requirements if r not in covered]
orphans = [name for name, reqs, _ in rvm if not reqs]
print(f"coverage {len(covered)}/{len(requirements)} = {len(covered) / len(requirements):.0%}")
print("requirements without verification:", missing)
print("activities with no requirement:", orphans)
coverage 6/8 = 75%
requirements without verification: ['R2', 'R3']
activities with no requirement: ['T4 motor noise log']
R2 and R3 have no verification yet (in module 2 these were the poorly written requirements; they must be rewritten to be measurable first). T4 verifies no requirement; it may be unnecessary work, or there may be a missing noise requirement.
Risk and FMEA
FMEA (failure modes and effects analysis), as defined in IEC 60812:2018, works through how each part can fail, what the effect is and how the failure can be prevented or detected. The traditional method rates severity (S), occurrence (O) and detection (D) from 1 to 10 and multiplies them into an RPN. The AIAG-VDA FMEA Handbook (2019) replaced this with Action Priority (AP), because equal RPNs can come from very different severities.
Example 2. A simple FMEA
fmea = [ # (failure mode, S, O, D)
("GNSS loss near tall trees", 8, 4, 3),
("companion computer hangs", 6, 3, 4),
("battery sag in wind", 9, 2, 2),
("AI misses a crack", 5, 5, 6),
("camera trigger drift", 4, 5, 5),
]
ranked = sorted(fmea, key=lambda row: row[1] * row[2] * row[3], reverse=True)
for mode, s, o, d in ranked:
flag = " <- severity 9+: act regardless of RPN" if s >= 9 else ""
print(f"RPN {s * o * d:>3} S{s} O{o} D{d} {mode}{flag}")
RPN 150 S5 O5 D6 AI misses a crack
RPN 100 S4 O5 D5 camera trigger drift
RPN 96 S8 O4 D3 GNSS loss near tall trees
RPN 72 S6 O3 D4 companion computer hangs
RPN 36 S9 O2 D2 battery sag in wind <- severity 9+: act regardless of RPN
Ranked by RPN alone, “battery sag in wind” comes last even though it has the highest severity (the drone could fall). This is why the newer method puts severity first. For operational risk as a whole, JARUS SORA 2.5 is the international framework, and the CAAT PDRA guidance applies to beyond-visual-line-of-sight flights in Thailand.
Methodology and development plan
A project proposal needs a methodology that says how the team will produce a system that meets the requirements, and a development plan that says who does what, when and with what resources. Both must be built from the deliverables of modules 1–5, not attached as stand-alone tables.
The methodology has four parts:
- Development approach: choose a life cycle that suits the risks, for example the V model (Figure 1) for parts with clear requirements, and short iterations with prototypes for uncertain parts such as the AI crack model. Each iteration must end with something that can be tested
- Work steps tied to requirements: every step says which requirement it serves, using the traceability matrix from module 4
- Data collection and analysis for each success criterion, stating the measure, sample size and calculation in advance, for example R1 measures recall on a user-approved test image set containing a stated number of labelled cracks, and R6 measures coordinate error against a stated number of surveyed points. Research-design texts ask for data collection and analysis to be stated in the proposal before the work starts (Creswell and Creswell, 2022)
- Tools, sites and permissions, such as drones, software, test sites, flight permission from CAAT and handling the personal data of the canal-side community
The development plan, following the NASA Systems Engineering Handbook, which records technical planning in a systems engineering management plan (SEMP) (NASA, 2016), has four parts:
- Work breakdown structure (WBS): NASA describes it as a product-oriented family tree that identifies the hardware, software, services and all other deliverables required to achieve the project objective, organised by product, not by activity (NASA, 2025, section 2.1). The lowest-level items are work packages, the units the project assigns and controls, which should match the components in the module 4 architecture
- Sequence and duration: state which work package must wait for which, then find the critical path, the longest chain of work; any delay on it delays the end of the project by the same amount, while packages off it have slack and can move without changing the end date (Kerzner, 2025). It is found with a forward pass for the earliest finish times and a backward pass for the latest finish times that do not delay the end
- Milestones with verifiable results, such as passing HITL testing, and a schedule margin before the deadline
- Resources and budget: people, equipment, survey costs and a contingency reserve matched to the risks identified in the FMEA (PMI, 2025)
Example 3. Next semester’s schedule and the critical path
The work packages come from the components in module 4. Next semester has 15 weeks; durations and prices are the team’s estimates (assumed), with a 15% contingency (assumed).
wps = { # id: (work package, weeks, depends on), listed so that predecessors come first
"WP1": ("airframe and camera mount", 3, []),
"WP2": ("mission software in SITL", 4, []),
"WP3": ("crack model training", 5, []),
"WP4": ("HITL and integration", 2, ["WP1", "WP2"]),
"WP5": ("onboard AI integration", 2, ["WP3", "WP4"]),
"WP6": ("field tests and validation", 3, ["WP5"]),
"WP7": ("final report and defence", 2, ["WP6"]),
}
early = {} # forward pass: earliest finish
for k, (_, weeks, deps) in wps.items():
early[k] = max((early[p] for p in deps), default=0) + weeks
end = max(early.values())
late = {k: end for k in wps} # backward pass: latest finish
for k in reversed(list(wps)):
for p in wps[k][2]:
late[p] = min(late[p], late[k] - wps[k][1])
for k, (task, weeks, _) in wps.items():
slack = late[k] - early[k]
print(f"{k} {task:27s} weeks {early[k] - weeks:>2}-{early[k]:>2} slack {slack}{' critical' if slack == 0 else ''}")
print(f"finish in week {end} of 15, schedule margin {15 - end} weeks")
budget = {"camera and mount": 18000, "companion computer": 9000, "spare batteries": 12000, "RTK checkpoint survey": 6000}
base = sum(budget.values())
print(f"budget {base:,} baht + 15% contingency = {base * 1.15:,.0f} baht")
WP1 airframe and camera mount weeks 0- 3 slack 1
WP2 mission software in SITL weeks 0- 4 slack 0 critical
WP3 crack model training weeks 0- 5 slack 1
WP4 HITL and integration weeks 4- 6 slack 0 critical
WP5 onboard AI integration weeks 6- 8 slack 0 critical
WP6 field tests and validation weeks 8-11 slack 0 critical
WP7 final report and defence weeks 11-13 slack 0 critical
finish in week 13 of 15, schedule margin 2 weeks
budget 45,000 baht + 15% contingency = 51,750 baht
The week numbers count from the start of semester. The work ends in week 13, leaving a 2-week margin. The critical path is WP2 → WP4 → WP5 → WP6 → WP7, so the mission software must start in week 1 and be watched most closely. WP1 and WP3 have 1 week of slack; if labelling images to train the model runs more than 1 week late, the end date slips too. The 2-week margin and the contingency should be tied to the high-severity risks in the FMEA of Example 2; for example, GNSS loss near tall trees may force a repeat field test. The budget including contingency is 51,750 baht.
The project proposal
The proposal brings together the deliverables of modules 1–5. Part 6 of Figure 2 (schedule and resources) is the methodology and development plan from the previous section (Example 3), and the risks use the FMEA from Example 2. The key principle is that every part must trace back to the requirements, and the proposal must state the conditions under which the project will be stopped or reviewed.
Module lab
Project deliverable: complete project proposal
- Build an RVM for every requirement and use Example 1 to check 100% coverage with no activities lacking a requirement
- Plan testing with the V model and the test ladder, setting the pass criterion for each step before testing
- Carry out an FMEA of at least 10 failure modes, rank them and give mitigations for every high-severity mode
- Write the methodology, build the WBS, a schedule with its critical path and a budget with contingency using the Example 3 code, then assemble the proposal following Figure 2
- Present to the committee for 15 minutes, answer questions, then revise the proposal based on their advice
Common mistakes
Watch out
- Requirements with no verification method in the RVM
- Setting pass criteria after seeing the test results
- Ranking risk by RPN alone and overlooking high severity
- Proposal sections that do not connect, such as a test plan that does not match the requirements
- No conditions for stopping or reviewing the project
- A schedule with no margin, or tasks ordered without checking which must wait for which, so nobody knows which are on the critical path
Summary
- The V model pairs every design layer with verification at the same level
- An RVM must cover every requirement, and every activity must have a requirement behind it
- FMEA works through failure modes; the newer method uses Action Priority, which puts severity first
- The methodology states the approach, steps tied to requirements and how results are measured; the development plan uses a product-based WBS, the critical path, a schedule margin and a contingency reserve
- The project proposal brings all deliverables together, traces back to the requirements and includes stop or review conditions
Check your understanding
- There are 20 requirements and verification activities cover 17 of them. What is the coverage?
- Work package A takes 3 weeks and B takes 4; both must finish before C, which takes 2. When can C finish at the earliest, and how much slack does A have?
- Why did the AIAG-VDA Handbook (2019) move from RPN to Action Priority?
- In the V model, which verification layer is paired with the system requirements?
- What does a test activity that verifies no requirement indicate?
Answers
- C can start when B finishes in week 4, so it finishes in week ; A has week of slack
- Equal RPNs can come from very different severities; the new method puts severity first
- System verification
- It may be unnecessary work, or a requirement may be missing
Key formulas
| Risk priority number (traditional) | |
| Slack of a work package | |
| Test plan coverage |
Key references
- National Aeronautics and Space Administration. (2016). NASA systems engineering handbook (NASA/SP-2016-6105 Rev 2). link
- National Aeronautics and Space Administration. (2025). NASA work breakdown structure (WBS) handbook (NASA/SP-20250006071). link
- International Organization for Standardization. (2023). Systems and software engineering — System life cycle processes (ISO/IEC/IEEE 15288:2023). link
- International Electrotechnical Commission. (2018). Failure modes and effects analysis (FMEA and FMECA) (IEC 60812:2018). link
- AIAG & VDA. (2019). FMEA handbook (1st ed.). Automotive Industry Action Group. link
- Joint Authorities for Rulemaking on Unmanned Systems. (2024). JARUS guidelines on Specific Operations Risk Assessment (SORA), main body, edition 2.5 (JAR-DEL-SRM-SORA-MB-2.5). link
- สำนักงานการบินพลเรือนแห่งประเทศไทย. (2568). แนวปฏิบัติในการขอปฏิบัติการบินอากาศยานซึ่งไม่มีนักบินโดยใช้การประเมินความเสี่ยงที่เป็นไปตามเงื่อนไขที่กำหนดสำหรับการบินเกินกว่าระยะสายตา (CAAT-GM-UAS-PDRA101 ปรับปรุงครั้งที่ 00). link
- ABET. (2025). Criteria for accrediting engineering technology programs, 2026–2027. link
- Creswell, J. W., & Creswell, J. D. (2022). Research design: Qualitative, quantitative, and mixed methods approaches (6th ed.). SAGE. link
- Kerzner, H. (2025). Project management: A systems approach to planning, scheduling, and controlling (14th ed.). Wiley. link
- Project Management Institute. (2025). A guide to the project management body of knowledge (PMBOK guide) (8th ed.). link
Further reading
Study the assigned knowledge units in advance, review media and take the module quiz
UAV testing and evidence analysis
การบริหารโครงการเทคโนโลยี
Evidence-based risk assessment
Project governance and monitoring
In class / field
Team project work, advisor meetings and progress presentations
Learning evidence: Project milestone deliverables