UAT 494 Unmanned Aircraft Systems and Automation Technology Capstone Project II

Worksheet 1 The first flyable increment

Lab 18 hAssesses CLO1

Objective

Split the plan into testable increments, update mass and energy budgets from real parts, build the first flyable increment and track progress with earned value

Equipment and materials

  • Plan and RVM from UAT 493
  • Prototype parts and a digital scale
  • SITL and a ground station
  • Python and the module 1 example code
  • Work-hours log sheet

Safety

  • Always test in SITL before real flight
  • Fly only in permitted areas within CAAT conditions in visual line of sight
  • Propellers off during assembly and setup; keep lithium batteries in fire-safe containers

Steps

  1. Split the plan into at least three increments, each with a testable 'working' criterion
  2. Weigh every real part; update the mass budget with Example 1 and the energy budget to match
  3. Build increment 1, test it in SITL, then fly in a permitted area
  4. Log work hours weekly; compute SPI and CPI with Example 2
  5. Meet the advisor every two weeks with progress figures

Record of results

Table 1 Increment plan and 'working' criteria
IncrementWhat it addsTestable 'working' criterionTest method (SITL or real flight)Result and date
Table 2 Mass budget from real parts
PartProposal estimate (g)Weighed mass (g)Difference (g)
Table 3 Weekly progress (earned value)
WeekPV (h)EV (h)AC (h)SPICPI

Questions

  1. From Table 2, find the mass margin using both the proposal estimate and the weighed mass. Does the margin still reach your team's minimum? Which part changed most, and why was it missing from the proposal?

  2. If the margin is below the target, what options does the team have? Which does it choose, and which part of the energy budget and flight time must be re-checked, and why?

  3. From the latest SPI and CPI in Table 3, how is the team behind schedule or over its planned effort? What is the estimate at completion (EAC), and which scope items would you cut first in MoSCoW order?

  4. Why must every increment be flyable and testable? If time ran out today, which increment would the team show the committee, and which of its criteria has it already proved?

Check before you hand in

What to hand in

  • Increment plan with criteria
  • Mass and energy budgets from real parts
  • SITL and real flight logs for increment 1
  • SPI/CPI table and meeting minutes

CLO1 Develop and integrate the prototype. (CLOs are a web-team draft; the course owner sets the final ones.)