UAT 316 Technology Project Management, Innovation and Entrepreneurship
Worksheet 1 Planning the service-unit project
Objective
Write a project charter, break down work with a WBS, analyse the critical path under delay and choose predictive or agile approaches
Equipment and materials
- The drone survey service-unit case in the lesson
- Computer with Python and the example code at /downloads/uat-316/
- Paper or a spreadsheet
Safety
- Desk work only; no flying
Steps
- Write a one-page charter with goal, scope, exclusions, deliverables and measurable success criteria
- Extend the WBS in Figure 1 one level and check each package has a single owner
- Estimate procurement time with the three-point method of Example 1
- Assume permits are two weeks late; recompute the critical path with the lesson code and propose one way to speed up
- Give each work package a number of people, draw the resource histogram with the code in Example 2, and propose smoothing, levelling or adding people
- Discuss which parts suit a predictive approach and which suit agile
Record of results
| Group in Figure 1 | Work package | Deliverable | Single owner | Duration (weeks) | People |
|---|---|---|---|---|---|
| Task | Duration (weeks) | ES / EF before | Float before | ES / EF after | Float after |
|---|---|---|---|---|---|
Questions
After the two-week permit delay, in which week does the project finish and does the critical path change? Why does speeding up procurement, the longest task, not bring the finish forward?
Why is the PERT expected time for procurement longer than the most likely value? Comparing it with task B's float before and after the permit delay, how does the risk of procurement becoming critical change?
In your histogram, which weeks are short of people? What happens to the finish date with smoothing and with levelling, and which option would your group take to the sponsor, and why?
Which parts of the service-unit project should be predictive and which agile? Give reasons based on how clear the requirements of each part are.
Check before you hand in
What to hand in
- One-page charter
- WBS with owners
- Critical path before and after the delay, with the speed-up option
- Conclusion on approach
- Resource histogram and over-allocation options with their effect on the finish date