UAT 316 Technology Project Management, Innovation and Entrepreneurship

Worksheet 2 A project review meeting

Analysis activity 3 hAssesses CLO1, CLO3

Objective

Report status with EVM, answer management with numbers, update the risk register and set KPIs and stop conditions

Equipment and materials

  • Week-6 status data from Example 1
  • The knowledge unit on project governance and monitoring
  • Calculator or the module 2 example code

Safety

  • Desk work and role-play; no flying

Steps

  1. Take the roles of project manager, executive and auditor
  2. The manager reports week-6 status with EVM figures
  3. Compute the CPI required on the remaining work to finish on budget (remaining work divided by remaining money)
  4. Add two risks to the register with owners and responses
  5. Write three KPIs and two stop conditions following the knowledge unit
  6. Write a quality plan with at least three acceptance criteria and how each is checked, and a five-activity RACI checked with the code in Example 3

Record of results

Table 1 EVM status at week 6 and the required CPI
MeasureFormulaValue (with unit)What it means for management
Table 2 Updated risk register
IDCause / event / impactLikelihood (1-5)Impact (1-5)Score and levelOwner and response
Table 3 Five-activity RACI and check result
ActivityProject managerChief pilotData analystMunicipal engineerCheck (one A, at least one R)

Questions

  1. How far is the CPI required on the remaining work from the current CPI? Is it realistic, and what should the manager propose to management?

  2. Has one of your stop conditions been triggered by the week-6 figures? If not, what would have to happen for it to trigger?

  3. Is there a risk in your register that does not have the top score but should be treated first? Why?

  4. On-time delivery is 90% but first-pass acceptance only 75%. What does each tell you, and which KPI did your group use for a stop condition, and why?

  5. What problem did your RACI check find and how did you fix it? If the team grows from 4 to 9 people, how do the communication channels change, and what does that mean for the communication plan?

Check before you hand in

What to hand in

  • One-page status report
  • Required CPI calculation
  • Updated risk register
  • KPIs and stop conditions
  • Quality plan and checked RACI

CLO1 Plan and manage technology projects. CLO3 Assess cost, risk and feasibility. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack