UAT 316 Technology Project Management, Innovation and Entrepreneurship
Worksheet 2 A project review meeting
Objective
Report status with EVM, answer management with numbers, update the risk register and set KPIs and stop conditions
Equipment and materials
- Week-6 status data from Example 1
- The knowledge unit on project governance and monitoring
- Calculator or the module 2 example code
Safety
- Desk work and role-play; no flying
Steps
- Take the roles of project manager, executive and auditor
- The manager reports week-6 status with EVM figures
- Compute the CPI required on the remaining work to finish on budget (remaining work divided by remaining money)
- Add two risks to the register with owners and responses
- Write three KPIs and two stop conditions following the knowledge unit
- Write a quality plan with at least three acceptance criteria and how each is checked, and a five-activity RACI checked with the code in Example 3
Record of results
| Measure | Formula | Value (with unit) | What it means for management |
|---|---|---|---|
| ID | Cause / event / impact | Likelihood (1-5) | Impact (1-5) | Score and level | Owner and response |
|---|---|---|---|---|---|
| Activity | Project manager | Chief pilot | Data analyst | Municipal engineer | Check (one A, at least one R) |
|---|---|---|---|---|---|
Questions
How far is the CPI required on the remaining work from the current CPI? Is it realistic, and what should the manager propose to management?
Has one of your stop conditions been triggered by the week-6 figures? If not, what would have to happen for it to trigger?
Is there a risk in your register that does not have the top score but should be treated first? Why?
On-time delivery is 90% but first-pass acceptance only 75%. What does each tell you, and which KPI did your group use for a stop condition, and why?
What problem did your RACI check find and how did you fix it? If the team grows from 4 to 9 people, how do the communication channels change, and what does that mean for the communication plan?
Check before you hand in
What to hand in
- One-page status report
- Required CPI calculation
- Updated risk register
- KPIs and stop conditions
- Quality plan and checked RACI