Module 2/5 · Weeks 4–6 · 27 h

Governance and monitoring

UAT 316 Technology Project Management, Innovation and Entrepreneurship

About 90 minDraft, awaiting reviewLast updated 2 October 2026

Lesson

By the end of this module you will be able to

  1. Measure performance with earned value management (EVM) and forecast the cost at completion
  2. Set KPIs with a definition, denominator, data source and review frequency
  3. Plan and control project quality with acceptance criteria, the cost of quality and a Pareto analysis
  4. Build a risk register following the ISO 31000 process and rank risks with a likelihood–impact matrix
  5. Assign team roles with a RACI matrix, plan communication, handle conflict and engage stakeholders
  6. Control changes and set conditions for stopping a project

Prerequisites: UAT 316 module 1

Why this matters

The best plan drifts once real work starts. The question executives ask is not “are you following the plan?” but “how far ahead or behind are you, and where will you end up if this continues?” Saying “we have spent half the money” means nothing without knowing how much work has been done. This module gives you the numbers to answer that, and the mechanisms that let a project stop in time when it should.

Earned value management

Earned value management (EVM) compares three values at the same point in time, as set out in the cost-estimating guide of the US Government Accountability Office (GAO):

  • PV (planned value): the value of work the plan says should be done by now
  • EV (earned value): the value of work actually done, at its budgeted cost
  • AC (actual cost): the money actually spent
  • BAC (budget at completion): the total project budget
A chart with weeks 0 to 12 on the horizontal axis and money from 0 to 1.2 million baht on the vertical. A blue PV line rises straight to 1.2 million at week 12. At week 6, PV is 600,000; the green EV line reaches 540,000 and the orange AC line 620,000. A summary box shows CPI 0.87, SPI 0.90 and EAC about 1,377,778
Figure 1 Earned value at week 6 (baht)

Example 1 Project status at week 6

The service-unit project has a total budget of 1,200,000 baht, planned to be spent evenly over 12 weeks. At week 6, 45% of the work is done and 620,000 baht has been spent.

bac = 1_200_000
pv = bac * 6 / 12
ev = bac * 0.45
ac = 620_000
cv, sv = ev - ac, ev - pv
cpi, spi = ev / ac, ev / pv
eac = bac / cpi
print(f"PV {pv:,.0f}  EV {ev:,.0f}  AC {ac:,.0f}")
print(f"CV {cv:+,.0f}  SV {sv:+,.0f}  CPI {cpi:.3f}  SPI {spi:.3f}")
print(f"EAC {eac:,.0f}   VAC {bac - eac:+,.0f}")
PV 600,000  EV 540,000  AC 620,000
CV -80,000  SV -60,000  CPI 0.871  SPI 0.900
EAC 1,377,778   VAC -177,778

The negative CV and SV show the project is both over budget and behind schedule. A CPI of 0.871 means each baht spent earns only 0.87 baht of work. If performance continues like this, the project will finish at about 1.38 million baht, almost 178,000 baht over budget. EAC = BAC/CPI assumes past efficiency continues; if the cause has been fixed, use another forecast. SV is measured in money, not time.

KPIs you can decide with

A key performance indicator (KPI) needs a definition, a denominator, a data source, an owner and a review frequency. An example from the drone knowledge hub’s unit on project governance and monitoring: a survey project delivered 20 sets, 15 passed the first check, 18 were on time, and 2 are still waiting for coordinate confirmation.

delivered, first_pass, on_time, pending = 20, 15, 18, 2
print(f"first-pass acceptance {first_pass / delivered:.0%}")
print(f"on-time delivery      {on_time / delivered:.0%}")
print(f"pending confirmation  {pending} sets (not counted as passed)")
first-pass acceptance 75%
on-time delivery      90%
pending confirmation  2 sets (not counted as passed)

On-time delivery is 90% but first-pass acceptance only 75%: two different dimensions. Watching only timeliness hides that one job in four needs rework, and pending items must be counted separately, not as passed. More flights do not mean the users’ problem is being solved better either. KPIs must measure the outcome users need.

Managing project quality

Quality here means that deliverables meet their requirements and are fit for the user’s purpose. PMBOK8 makes “embed quality” one of its six principles: quality is built into the work from the start, not inspected in at the end. Quality work in a project has three parts, as ASQ defines them:

  • Quality planning sets measurable acceptance criteria for every deliverable before work starts, so that the team and the client judge by the same yardstick
  • Quality assurance (QA) is the planned, systematic activity that gives confidence the work will meet those requirements, such as standard operating procedures, checklists, training and internal audits. It looks at how the work is done
  • Quality control (QC) inspects and measures the outputs against the criteria and records every defect. It looks at what came out

For the survey unit, a quality plan for the orthophoto map might read (figures assumed for practice):

Deliverable characteristicAcceptance criterionHow it is checked
Ground sampling distanceNo coarser than 3 cmRead from the processing report
Position accuracyHorizontal RMSE at independent checkpoints no more than 5 cmSurvey at least 5 checkpoints not used in processing
Coverage100% of the agreed boundary, no gapsOverlay the map on the boundary file
FormatGeoTIFF with the coordinate system statedOpen in GIS software

The cost of quality (COQ) shows where quality money goes. ASQ splits it into four kinds: prevention (planning, training, procedures), appraisal (checking and measuring), internal failure (defects found before delivery: rework and re-flying) and external failure (defects the client finds: complaints, free re-surveys and lost trust). A Pareto chart, one of the basic quality tools that Ishikawa (1976) taught, sorts the causes of defects from most to least frequent so the team fixes the few causes behind most of the problems first.

Example 2 Where are the rejections coming from?

In the first three months of service (assumed), the unit delivered 40 map sets. Internal QC rejected 12 of them before delivery (rework costs 2,500 baht each), and the municipality found 2 more errors after delivery (10,000 baht each to re-survey). Checking each set against the checkpoints costs 750 baht, and training plus writing procedures cost 20,000 baht.

rejections = {"checkpoint error over limit": 5, "gap in coverage": 3, "blurred images": 2,
              "wrong file format": 1, "missing metadata": 1}
total = sum(rejections.values())
cumulative = 0
for cause, n in sorted(rejections.items(), key=lambda kv: kv[1], reverse=True):
    cumulative += n
    print(f"{cause:<28} {n:>2}  cumulative {cumulative / total:.0%}")

cost = {"prevention": 20_000, "appraisal": 40 * 750, "internal failure": 12 * 2_500, "external failure": 2 * 10_000}
coq = sum(cost.values())
for kind, baht in cost.items():
    print(f"{kind:<17} {baht:>7,} baht  {baht / coq:.0%}")
failure = cost["internal failure"] + cost["external failure"]
print(f"cost of quality {coq:,} baht, of which failure {failure:,} baht ({failure / coq:.0%})")
checkpoint error over limit   5  cumulative 42%
gap in coverage               3  cumulative 67%
blurred images                2  cumulative 83%
wrong file format             1  cumulative 92%
missing metadata              1  cumulative 100%
prevention         20,000 baht  20%
appraisal          30,000 baht  30%
internal failure   30,000 baht  30%
external failure   20,000 baht  20%
cost of quality 100,000 baht, of which failure 50,000 baht (50%)

Two causes, checkpoint errors and coverage gaps, account for two thirds of rejections, so the team should fix those first: retrain the ground-control procedure and check coverage in the field before leaving the site. Half of the cost of quality is failure cost, money spent on getting things wrong. An extra 10,000 baht of prevention is worthwhile if it removes more than 10,000 baht of failure cost, for example 4 fewer rejections (10,000 baht) plus one fewer external failure (another 10,000 baht). External failures matter most, because the client loses trust as well as the unit losing money.

Risks and stakeholders

ISO 31000:2018 sets the risk-management process as identifying, analysing, evaluating and treating risks, with continuous communication and monitoring. A risk register records each risk, separating cause, event and impact, as in UAT 313 module 3.

A five-by-five matrix with likelihood 1 to 5 on the vertical axis and impact 1 to 5 on the horizontal. Each cell shows the product score, coloured from green for low through yellow and orange to pink for high. R1 sits at likelihood 4, impact 4, score 16; R2 at likelihood 2, impact 5, score 10; R3 at likelihood 3, impact 2, score 6
Figure 2 Risk matrix: likelihood × impact
risks = [
    ("R1", "permit delayed", 4, 4, "file early, assign an owner, weekly follow-up"),
    ("R2", "drone crash during pilot service", 2, 5, "OM, checklists, insurance, geofence"),
    ("R3", "mapping software price rises", 3, 2, "compare two vendors, budget reserve"),
]
for rid, event, likelihood, impact, response in sorted(risks, key=lambda r: r[2] * r[3], reverse=True):
    score = likelihood * impact
    level = "high" if score >= 15 else "medium" if score >= 8 else "low"
    print(f"{rid} score {score:>2} ({level:<6}) {event:<32} -> {response}")
R1 score 16 (high  ) permit delayed                   -> file early, assign an owner, weekly follow-up
R2 score 10 (medium) drone crash during pilot service -> OM, checklists, insurance, geofence
R3 score  6 (low   ) mapping software price rises     -> compare two vendors, budget reserve

Scores help rank risks but are not the whole story. R2 scores 10, lower than R1, but has the highest impact (people could be hurt), so it needs controls even though it is unlikely. The level bands here are practice thresholds; each organisation must set its own.

Stakeholders of the service unit include the mayor, communities being flown over, the Civil Aviation Authority of Thailand (CAAT), equipment vendors and the pilot team. A common tool is the power–interest grid: high-power, high-interest groups need close management, while low-power groups that are affected, such as communities, need regular information.

Managing the team and engaging stakeholders

A project is delivered by people, and “build an empowered culture” is another of PMBOK8’s principles. Managing the team covers four things.

1. Clear roles. A responsibility assignment matrix, usually written as RACI, gives each person one of four letters for each activity: R (responsible) does the work, A (accountable) owns the result and signs it off, C (consulted) is asked before a decision, and I (informed) is told afterwards. Every activity must have exactly one A and at least one R. Two A’s means nobody really owns the result; no R means nobody does the work. This extends the rule from module 1 that every work package has a single owner.

2. A team that grows together. Tuckman (1965) observed that small groups pass through stages he called forming (polite and unsure of roles), storming (disagreement over roles and methods), norming (agreed ways of working) and performing (working well together). Tuckman and Jensen (1977) later added adjourning when the group disbands. Storming is normal, not a sign of failure; the manager’s job is to help the team through it, for example by agreeing roles and a way to decide at the first meeting.

3. Communication that scales. Each pair of people is a communication channel, so a team of has channels, and the number grows much faster than the team. A communication plan says who needs which information, when, in what form and from whom, such as a daily flight briefing for pilots and a monthly status report for the mayor.

4. Handling conflict. The Thomas–Kilmann model describes five conflict modes along two dimensions, assertiveness (pursuing your own concerns) and cooperativeness (attending to the other side’s concerns): competing, collaborating, compromising, avoiding and accommodating. No single mode is always right. When the chief pilot wants to cancel a flight because the wind is over the aircraft’s limit and the municipality wants the job done today, safety must not be split down the middle: the pilot-in-command’s decision stands (competing is justified), and the team then collaborates on a new date and on warning the client earlier next time. A dispute over report layout can simply be compromised.

Engaging stakeholders goes beyond the power–interest grid above. For each group, the plan records what they need to know, their current attitude, the attitude the project needs, the method (meeting, notice, community forum), how often, and who is responsible. Communities under the flight path, for example, need notice of flight dates and a channel for complaints before the first flight, not after the first complaint.

Example 3 Checking the RACI and counting channels

The draft RACI of the survey unit has four activities and four roles. The code checks the two rules and counts channels as the team grows.

raci = {
    "flight plan and permit": {"project manager": "A", "chief pilot": "R", "data analyst": "I", "municipal engineer": "C"},
    "survey flights": {"project manager": "I", "chief pilot": "A", "data analyst": "C", "municipal engineer": "I"},
    "map processing": {"project manager": "A", "chief pilot": "C", "data analyst": "R", "municipal engineer": "A"},
    "acceptance check": {"project manager": "R", "chief pilot": "I", "data analyst": "R", "municipal engineer": "A"},
}
for task, roles in raci.items():
    codes = list(roles.values())
    problems = []
    if codes.count("A") != 1:
        problems.append(f"{codes.count('A')} accountable")
    if "R" not in codes:
        problems.append("nobody responsible")
    print(f"{task:<24} {'ok' if not problems else ', '.join(problems)}")

for n in (4, 6, 9):
    print(f"team of {n}: {n * (n - 1) // 2} communication channels")
flight plan and permit   ok
survey flights           nobody responsible
map processing           2 accountable
acceptance check         ok
team of 4: 6 communication channels
team of 6: 15 communication channels
team of 9: 36 communication channels

“Survey flights” has an owner but nobody assigned to fly, so the chief pilot should be both R and A, or a named pilot should be R. “Map processing” has two A’s, the project manager and the municipal engineer; the engineer should be C, giving views on the requirements, while the project manager stays A. Growing the team from 4 to 9 people raises the channels from 6 to 36, six times as many, which is why larger teams need a written communication plan and clear points of contact.

Change control and stop conditions

Every change to scope, time or budget must go through change control: log the request, assess its impact, have someone with authority approve it, then update the plan. Accepting small additions bit by bit without the process is scope creep, a leading cause of cost overruns.

A good project sets stop or review conditions from the start, such as “if CPI is below 0.85 for two reviews in a row, review the scope” or “if first-pass acceptance in the pilot is below 70%, stop expanding”. Stopping an ineffective project early is a good decision, not a failure.

Class activity

Activity: a project review meeting

  1. Take the roles of project manager, executive and reviewer. The project manager reports the week-6 status from Example 1 using EVM figures.
  2. The executive asks what CPI the remaining work needs to finish within the original budget. Groups calculate it (remaining work divided by remaining money).
  3. Add two more risks to the register, each with an owner and a response.
  4. Write three KPIs and two stop conditions for the project, following the hub’s unit on project governance and monitoring.
  5. Write a quality plan with at least three acceptance criteria and how each is checked, then a RACI for five activities of the project; check it with the code in Example 3 and agree how the team will decide when it disagrees.

Common mistakes

Watch out

  • Reporting money spent without work done, so nobody knows if the project is over budget
  • Reading SV as days, when it is in money
  • Setting KPIs that count activity, such as flights, instead of outcomes users need
  • Checking quality only at the end, so defects are found when fixing them costs most
  • Giving one activity two accountable people, so neither owns the result
  • Ranking risks by score alone, overlooking risks with severe impact
  • Adding work without change control

Summary

  • EVM compares PV, EV and AC to give CV, SV, CPI and SPI, and forecasts the final cost with EAC = BAC/CPI
  • KPIs need a definition, denominator, data source and review frequency, and must measure what users need
  • Quality is planned as acceptance criteria, assured through the process and controlled at the outputs; the cost of quality and a Pareto chart show where to invest in prevention
  • The risk register separates cause, event and impact, ranked by likelihood × impact plus judgement
  • A RACI gives every activity one A and at least one R; communication channels grow as ; choose the conflict mode that fits the situation, never compromising on safety
  • Control every change, and set stop or review conditions at the start of the project

Check your understanding

  1. With EV = 300,000 baht and AC = 250,000 baht, what are CPI and CV?
  2. A team grows from 5 to 8 people. How many communication channels are there before and after?
  3. With BAC = 2,000,000 baht and CPI = 0.8, what is EAC?
  4. A risk has likelihood 3 and impact 5. What is its score?
  5. Prevention costs 15,000 baht, appraisal 25,000, internal failure 40,000 and external failure 20,000. What is the cost of quality, and what share is failure cost?
Answers
  1. CPI and CV baht, under budget
  2. channels before and after
  3. baht
  4. baht, of which failure is

Key formulas

Cost of quality
Communication channels in a team of n
Cost and schedule variance
Performance indices
Estimate at completion (constant CPI)
Risk score

Key references

  1. U.S. Government Accountability Office. (2020). Cost estimating and assessment guide: Best practices for developing and managing program costs (GAO-20-195G). link
  2. Project Management Institute. (2025). A guide to the project management body of knowledge (PMBOK guide) (8th ed.). link
  3. International Organization for Standardization. (2018). Risk management – Guidelines (ISO 31000:2018). link
  4. Kerzner, H. (2025). Project management: A systems approach to planning, scheduling, and controlling (14th ed.). Wiley. link
  5. ISO. (2020). ISO 21502:2020 Project, programme and portfolio management — Guidance on project management. link
  6. ASQ. Quality assurance vs quality control: QA vs QC. ASQ quality resources. link
  7. ASQ. Cost of quality (COQ). ASQ quality resources. link
  8. ASQ. What is a Pareto chart? ASQ quality resources. link
  9. Ishikawa, K. (1976). Guide to quality control. Asian Productivity Organization. link
  10. Tuckman, B. W. (1965). Developmental sequence in small groups. Psychological Bulletin, 63(6), 384–399. https://doi.org/10.1037/h0022100 link
  11. Tuckman, B. W., & Jensen, M. A. C. (1977). Stages of small-group development revisited. Group & Organization Studies, 2(4), 419–427. https://doi.org/10.1177/105960117700200404 link
  12. Kilmann Diagnostics. An overview of the Thomas-Kilmann Conflict Mode Instrument (TKI). link

Further reading

Study the assigned knowledge units in advance, review media and take the module quiz

In class / field

Lecture, case discussion and in-class problem solving

Learning evidence: Quiz results and submitted exercises

Module quiz

This is a formative self-check, not a graded exam

Knowledge domain: Management, innovation and professional practice