UAT 491 Unmanned Aircraft Systems and Automation Technology Capstone Project
Worksheet 1 A one-page project proposal
Objective
Define a problem from real users with numbers, review literature systematically and scope the work to finish in one term
Equipment and materials
- User interview guide
- Literature databases and a reference manager
- Python and example code at /downloads/uat-491/
- One-page proposal template
Safety
- Desk work and interviews only; no flying
- Obtain consent before interviews and do not publish interviewees' personal data
Steps
- Interview at least two real users, record measurable current numbers and compute as in Example 1
- Write a who, what and why problem statement in at most three sentences
- Build a literature table of at least six real sources with DOIs or links
- Break the work into a WBS, estimate hours, compare with team hours using Example 2 with 12 h per person per week (8 supervised and 4 self-study under the 4(0-8-4) credit pattern) and trim scope to fit
- Submit the one-page proposal with a weekly plan to the advisor by week 3
Record of results
| Item measured | Value given by the user (with unit) | Interviewee and interview date | Yearly result (with unit) |
|---|---|---|---|
| Source (author, year, type) and DOI or link | Problem it addresses | Method used and result reported | What we reuse, or the gap |
|---|---|---|---|
| Work package | Hours before cuts | Hours after cuts | How it was cut (buy not build, reuse, or reduce output) |
|---|---|---|---|
Questions
Using Table 1, compute the yearly person-hours and money spent by the current method, then pick one number as the success criterion for the demo day. Why must it be labelled an estimate from interviews?
Compare your problem statement with a technology-first sentence such as "we want to build an AI drone to inspect roofs". Does yours state who, what and why, and what does it tell a reader that the technology sentence does not?
From Table 2, which source gave you a method to reuse and what gap will your project fill? What happens to the module 5 report if you cite a source you have not read yourself?
The team hours in this course use 12 hours per person per week from the 4(0-8-4) credit pattern. If the usable-time fraction u falls from 0.85 to 0.70 because waiting for parts and travel take more time than planned, how many team hours are left? Does your scope still fit, and if H_need exceeds H_team, which work did you cut and by which method?
Why did your group not cut the test campaign when time ran short? Answer by saying what the tests serve as evidence of in the proposal and in the final report.
Check before you hand in
What to hand in
- Interview notes and current numbers
- Literature table
- WBS and hour calculation
- One-page proposal with weekly plan