UAT 494 Unmanned Aircraft Systems and Automation Technology Capstone Project II

Worksheet 2 Integrate one part at a time

Lab 18 hAssesses CLO1

Objective

Define interfaces with an ICD, control configuration with baselines and change requests, and integrate while testing every interface

Equipment and materials

  • Prototype from worksheet 1 and subsystems to integrate
  • Version control (e.g. Git)
  • Multimeter and signal measurement tools
  • Python and the module 2 example code

Safety

  • Propellers off during integration and bench tests
  • First power-up after rewiring through a current limiter
  • Never fly a configuration not recorded as a baseline

Steps

  1. Write a short ICD for every interface (signal, data format, rate, voltage, connector)
  2. Set baseline v1.0 of firmware, software and parameters in version control
  3. Integrate in the Figure 1 order and test every interface with an Example 2 table
  4. Route every change through request, review and retest; compare configurations with Example 1 whenever results change
  5. Log open issues with owners

Record of results

Table 1 Interface control document (ICD)
InterfaceSignal and protocolData format and rateVoltage and connectorOwner of each side
Table 2 Interface test results and open issues
InterfaceRound 1 resultFix (change request no. and what was retested)Retest resultOpen issue, owner, due date
Table 3 Configuration comparison of two runs with different results
Configuration itemRun 1Run 2Changed?

Questions

  1. Calculate the pass rate in round 1 and after fixes from Table 2. Which interface is still an open issue? How would you write that issue so someone who does not know the project understands it, and why must it not be hidden?

  2. From Table 3, which items changed at the same time? How would you separate which one caused the difference, and how many experiments would that need?

  3. Why does this project integrate bottom-up and one part at a time? Give an example from your own build of a problem that was easy to trace because of this.

  4. After fixing one interface, which other interfaces does the team retest and why? Use the ICD to see which ones share a signal, port or power source.

Check before you hand in

What to hand in

  • ICD
  • Baseline v1.0 and change request history
  • Interface test table
  • Open issues list

CLO1 Develop and integrate the prototype. (CLOs are a web-team draft; the course owner sets the final ones.)

Instructors: answers and teaching notes for this worksheet are in the teaching pack