การบริหารโครงการเทคโนโลยี
Scope, schedule, cost, risk and project communication
Why it matters
A project is temporary work undertaken to create a unique result, with a start and an end. Operations, by contrast, repeat continuously. Setting up a survey flight unit, building a drone prototype and a final-year capstone are all projects. Most failed technology projects do not fail because the engineering is impossible. They fail because the scope is vague, the schedule is unrealistic, the budget has no reserve, risks have no owner, or the people involved are not kept informed.
This unit covers five things a project manager must handle at the same time: scope, schedule, cost, risk and communication. The main references are the PMBOK Guide, 8th edition (Project Management Institute, 2025), ISO 21502:2020 and Kerzner (2025).
Scope
Scope is everything the project must deliver and, just as important, what it will not do. It starts with the project charter, the document that authorises the work and states goals, deliverables, sponsor, rough budget and success criteria. Scope is then decomposed into a Work Breakdown Structure (WBS) organised by deliverable, down to work packages small enough to estimate and assign to one owner.
The enemy of scope is scope creep: work added bit by bit without adjusting time or budget, for example a client asking for thermal images on top of the agreed colour survey. The defence is change control. Every change request is written down, assessed for its effect on schedule, cost and risk, and approved by someone with authority before work starts.
Schedule
A schedule is built from WBS work packages, their dependencies and durations. The Critical Path Method (CPM) of Kelley and Walker (1959) finds the longest chain of dependent tasks. If a task on that chain slips, the whole project slips. Tasks off the chain have float and can slip a little. Projects with a software component often plan in short agile iterations and track them with a burndown chart. A good schedule has checkable milestones, such as passing the design review or the first successful test flight.
Cost
Estimate cost bottom-up from the WBS work packages, summed into the budget at completion (BAC). Then add a contingency reserve derived from the risk register, not an arbitrary percentage.
During execution, Earned Value Management (EVM) compares three values on the same date: PV (planned value) for the work scheduled, EV (earned value) for the work actually completed at budgeted cost, and AC (actual cost) for money spent. From these come CPI = EV / AC and SPI = EV / PV. A value below 1 means over budget or behind schedule.
Risk
ISO 31000:2018 defines risk as the effect of uncertainty on objectives. Risks are recorded in a risk register that separates cause, event and consequence, scores likelihood and impact, names an owner, and chooses one of four responses: avoid, reduce, transfer (for example through insurance) or accept.
When impact can be expressed in money, use the expected monetary value (EMV) = probability × cost if it occurs, and sum the EMVs into the contingency reserve.
Communication
The number of communication channels among n people is n(n − 1)/2. A team of six has 15 channels. Add the client, advisor, funder and regulator for eight parties in total and there are 28. A communication plan states who receives what, how often and through which channel. A RACI chart states who does the work (Responsible), who owns the outcome (Accountable), who must be asked first (Consulted) and who must be told (Informed). A good status report is short, uses numbers and states what decision the reader needs to make.
Example: a 10-week pilot project inspecting factory roofs by drone
All values are assumed. The baseline budget is BAC = 400,000 baht. The risk register has three risks that can be costed.
| Risk | Probability | Cost if it occurs (baht) | EMV (baht) |
|---|---|---|---|
| Flight permission delayed, crew on standby | 0.3 | 40,000 | 12,000 |
| Drone crash, replacement aircraft needed | 0.1 | 90,000 | 9,000 |
| Image processing must be redone | 0.4 | 15,000 | 6,000 |
| Total | 27,000 |
The contingency is 27,000 baht, so the total approved budget is 427,000 baht.
At the end of week 5: PV = 200,000 baht, EV = 170,000 baht, AC = 190,000 baht.
- CV = EV − AC = −20,000 baht and SV = EV − PV = −30,000 baht (SV is in money, not time).
- CPI = 170,000 / 190,000 ≈ 0.895 and SPI = 170,000 / 200,000 = 0.85.
- If performance stays the same, the estimate at completion is EAC = BAC / CPI ≈ 447,059 baht, about 20,059 baht above the 427,000 baht total. The contingency is not enough.
- To finish within the total, the remaining work of 400,000 − 170,000 = 230,000 baht must be done with the remaining 427,000 − 190,000 = 237,000 baht. The required efficiency is 230,000 / 237,000 ≈ 0.970, clearly above the current CPI.
The project manager should report to the sponsor now, not in week 10, with options: reduce the number of buildings, request more funds, or find and fix the root cause of the slow progress.
Common pitfalls
- No charter, so nobody has authority when scope conflicts arise.
- Accepting extra work verbally without change control.
- Using the most likely duration as the deadline with no allowance for uncertainty.
- No contingency, or a flat percentage unrelated to actual risks.
- A risk register with no owners, written once and never reviewed.
- Green status every week until the problems surface at the end.
Continue in the lessons
- UAT 309 Module 2: Literature review and conceptual framework
- UAT 316 Module 1: Project management (continuing programme)
- UAT 491 Module 3: Development and integration (four-year programme)
- UAT 493 Module 5: Test plan and proposal (continuing programme)
- UAT 497 Module 3: Work and defining the project
Key references
- Project Management Institute. (2025). A guide to the project management body of knowledge (PMBOK guide) (8th ed.). link
- Kerzner, H. (2025). Project management: A systems approach to planning, scheduling, and controlling (14th ed.). Wiley. link
- ISO. (2020). ISO 21502:2020 Project, programme and portfolio management — Guidance on project management. link
- International Organization for Standardization. (2018). Risk management – Guidelines (ISO 31000:2018). link
- Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. Papers presented at the Eastern Joint IRE-AIEE-ACM Computer Conference (pp. 160–173). link
- National Aeronautics and Space Administration. Earned value management reference card. link