M01 Survey and mapping: from the request to acceptance evidence
Choose the survey set, reference system and data-collection plan, then check the results with independent points, with KSEC worksheets for beginners, planners and developers.
What this mission answers and what it delivers
Start from the recipient's question about what decision the map must support, then agree together on the scope, deliverables, reference system and acceptance evidence. This chapter uses a hypothetical yard survey, planning a walk-through inspection of the area, as its example. The recipient needs an orthomosaic for seeing positions and context and a DSM of the visible surface together with a quality report and the parts still missing; it is not a certification of land boundaries or of engineering accuracy
Choose the pathway according to the work product: B Beginner produces a brief and explains the deliverables, O Practitioner/planner arranges the plan, people, resources and acceptance checks, D Developer/tuner produces the requirements, interfaces and test plan. All use the same shared data but assess the evidence according to their role. This activity involves no flying, hardware adjustment or real image processing
Read How to choose the set, C01-C10 and then use the MAP base on deliverables, image-capture plan and coordinates; the MAPQ base on receiving the brief, collecting data, processing and formula checks and handover; and the MAPV base on surface and volume so that a DSM is not used in place of the ground without evidence. This chapter links the earlier bases into a mission and KSEC activities without reviewing the whole earlier set again
The opening context image was created with AI to illustrate a review of the area and its boundary; it is not an image of the scenario site or real survey evidence. Open the full-size context image
If the work must be followed up over several rounds, read M05 Construction Monitoring to tie survey results to a work package/baseline/data date, with open items; proxy quantities and map results are neither accepted work nor approval of payment by themselves
It builds on the control and independent-check-point base in M08 Environmental Monitoring by adding season, water, sensor/class and ground reference. Survey results or RTK/PPK do not yet confirm plant species or restoration
Terms used in decisions
Scroll the table horizontally to see all columns. When the table has keyboard focus, use the left or right arrow keys
| Term | Meaning for this chapter | What to check |
|---|---|---|
| Orthomosaic | Several images geometrically adjusted and stitched into a map image | A continuous or sharp image does not yet tell positional accuracy |
| DSM | A model of the surface height that the system can build, such as roofs, plant canopy and open ground | Describe occluded areas and gaps; do not call every value ground |
| DTM | A terrain model of the ground, which requires separating above-ground objects and checking the result | A DSM is not automatically a bare-earth DTM |
| GSD | The ground distance between the centres of adjacent pixels, in m/px or cm/px | Uses the height above the actual ground or object, the camera and the terrain; it is not accuracy |
| GCP | Reference points used to control or adjust the processing result | The residual of points used for adjustment is not independent evidence |
| Independent checkpoint | Reference points held out of the adjustment and then used to assess after processing | State the measurement method, uncertainty, reference system, time and the extent the points represent |
Defines GSD and the camera/height-above-ground factors; cites PIX4D: Ground sampling distance separating control points from check points; cites WebODM: Ground Control Points and re-checks the deliverable details at Outputs from mapping drones A GSD of 2 cm/px does not mean the position is accurate to 2 cm and RTK/PPK do not replace acceptance checking with independent evidence
Seven steps of work and the hold points
Diagram description: every step has evidence and a responsible person; if the data is insufficient, go back and fill it in or hold the work before releasing results. Open the full-size process diagram
1. Receive the request and agree the deliverables
Record the recipient, objective, work scope, the date and freshness required, orthomosaic/DSM or another type of result, file-opening format, access rights and acceptance criteria. Treat image resolution, area completeness and positional accuracy as separate items. If a DTM beneath vegetation or values for certification are requested, review how the data would be obtained and involve a subject-specific reviewer; do not rename a DSM to match the order. Read Receiving the brief and survey acceptance criteria
2. Arrange people, resources, platform and camera
The planner must have people for data collection/work control, a reference surveyor, a QA checker, a processor and a recipient of the results. State who does and who checks in each phase, with a cross-check back when one person takes several roles. Keep a register of aircraft and cameras that have manuals, the set of reference/survey points, power, storage media, data backup, processing machines, the software versions used and the resources for rechecking. Costs should include site access time, coordination, surveying, image checking, processing, refly and data retention
Choose the aircraft type from the conditions of the actual set, not by ranking the type names:
- Multirotor: considers site access for take-off and landing and work that needs changes of viewpoint; check the mass/balance of the set, the camera, vibration, power and the support specified in the manual
- Fixed-wing: check the take-off, landing and recovery method, the turning area/pass lines, the speed the camera can support and payload limits; if the site or team cannot support it, hold this option
- VTOL: check the vertical take-off and landing phases, the transition phases and the fixed-wing phase, including the support area, power and support work of the actual design. Do not assume that having the properties of two types makes every mission easier
For this scenario, begin by considering RGB for context imagery and building the visible surface. multispectral is used when the question needs spectral-band data and there is a calibration plan/ground data, thermal is used when there is a thermal question and checkable measurement conditions, LiDAR is used when the result and site conditions need that method together with position/attitude and calibration; do not choose it merely because a sensor is available. Read payload and sensor limitations
If a camera with known specifications, a survey instrument, a checker, a processing machine or data storage is missing, reduce the scope, request resources, or compare a ground walk-through/survey and imagery that is already permitted, using the same question and criteria. Do not invent flight distances, battery counts or processing times for a set that is not yet known

An AI-created illustration, not an equipment register that confirms performance or compatibility. Open the full-size resource-set image
3. Check the area, reference system and data-collection plan
Separate the deliverable boundary from the boundary where imagery must be captured and from the take-off/landing/turning areas. Check terrain, obstacles, textureless surfaces, occluded parts and team access. Define the actual height above ground, camera angle, GSD, forward and side overlap, shooting distance/interval, speed and the refly checking frame. Images for a 2D map and a 3D shape may need different viewpoints. Read WebODM: Flying Tips
the document QGroundControl: Survey that separates camera values, overlap and turnaround and states the flat-ground assumption when planning from camera specifications. Use it as a basis for thinking, then check the manual and software version of the actual set before configuring. Do not treat terrain following as evidence of obstacle avoidance, and do not use the heights from the exercise as permitted values
Record the reference completely: the source and export coordinate frame/CRS, units, axis order and direction, horizontal datum, height type/vertical datum, geoid model and version where used, and the relevant time/offset/epoch, measurement method and uncertainty. Check that the points and the deliverable use the same definitions before computing differences A real export must have a confirmed CRS and height system ; do not assign an EPSG code to a hypothetical local frame to make it look like world coordinates. Read Coordinates and height
Hold checkpoints out of the adjustment from the start, with a plan for distributing them to cover the areas and height ranges to be claimed. Check independence, measurement method, time and uncertainty before use. A small RTK/PPK or GCP figure does not confirm the accuracy of the whole area. Read RTK, PPK, GCP and check points
The area, airspace, access rights, requirements and flight coordination of a real job must still be checked against the actual date, area, set and responsible persons. This chapter has no data confirming those things. The document CAAT: Operations Manual guidance (2022) is used to cite the structure for preparing the site, team, manuals and records; it is not used to confirm legal provisions or current numerical limits
4. Check the data during collection and before processing
Check image sharpness/blur, lighting, occlusion, continuity and overlap, time and file names, position/attitude if available, and the visibility of the targets as planned. Preserve original files and backups, check the list against the plan, then map the missing parts. Consider refly only if it is still within the conditions the team has approved; otherwise hold and report the limitation. Read Image quality and field work
5. Process and keep the trace
Use an image set whose rights and QA have been checked. Record the input, software version, values used, camera/calibration, the points used as control, the points held out, and the log. Check the deliverable for gaps, seams, distortions and the reference system before computing accuracy. Estimate working/spare space from real data and small trials; the number of images alone does not certify that any machine will process in time. Read Building the first map and processing lab . This M01 set has no images to run in WebODM and no new run results
6. Assess with independent points and the stated extent
Separate horizontal/vertical differences and bias. Count the points with complete values in each dimension. Keep missing points in an open-items list; do not replace gaps with zero and do not delete badly wrong points to pass. Also check the reference and the distribution of points. Results from a small sample or clustered points do not certify the areas not checked. If a checkpoint is used to correct the model, the status must be changed and independent evidence arranged for the reassessment. Read Checking accuracy
7. Deliver according to status and make it reopenable
Deliver the deliverables that actually exist, with the area boundary, units/CRS/height, time and source, data version, QA report, the control/checkpoint list and measurement method, limitations/NoData, rights and terms of use. The recipient opens and checks together before accepting. If the data is incomplete, send a status report or partial results with a clearly stated extent that do not yet certify the whole set. Read Acceptance and handover and data rights
Practising with a hypothetical yard and two options
The following scenario and figures were invented for practice : a flat engineering yard of 300 x 200 m with no world coordinates and no real flight, using the frame M01-LOCAL: origin at the lower-left corner, x axis to the right, y upward, z up, units in metres. The zero level is hypothetical, with no world datum/geoid/epoch or transformation parameters
The hypothetical recipient requests an orthomosaic to plan a walk-through inspection and a DSM of the visible surface. The example criteria set by the author are GSD <= 0.02 m/px, sample RMSE_H <= 0.10 m and sample RMSE_Z <= 0.15 m with check data complete within the scenario's scope. These criteria are not a survey standard or a field certification
Hypothetical camera: sensor 13.2 x 8.8 mm, model focal length 8.8 mm, image 6000 x 4000 px, nadir pinhole camera over flat ground, with the footprint width along x and length along y; H is the camera-to-ground distance. This formula excludes a real lens, tilt, uneven ground or vibration:
footprint_width_m = H_m × sensor_width_mm / focal_mm
footprint_length_m = H_m × sensor_height_mm / focal_mm
GSD_m_per_px = footprint_width_m / image_width_px
photo_step_m = footprint_length_m × (1 − front_overlap)
line_spacing_m = footprint_width_m × (1 − side_overlap)
interval_s = photo_step_m / speed_m_per_s
Scroll the table horizontally to see all columns. When the table has keyboard focus, use the left or right arrow keys
| Same values/conditions | Plan A | Plan B |
|---|---|---|
| H above hypothetical ground | 80 m | 60 m |
| Footprint width x length | 120 × 80 m | 90 × 60 m |
| GSD | 0.020 m/px (2 cm/px) | 0.015 m/px (1.5 cm/px) |
| Front / side overlap given by the scenario | 80% / 70% | 80% / 70% |
| Photo step / line spacing | 16 / 36 m | 12 / 27 m |
| Hypothetical speed | 5 m/s | 5 m/s |
| Shooting interval from the geometry | 3.2 s | 2.4 s |
| Result against the scenario's GSD criterion | Passes numerically | Passes numerically |
| Trigger manual, battery, turning/launch area, terrain and actual weather | No evidence yet | No evidence yet |
Both options pass only the invented GSD. According to the model, B needs a shorter shooting interval than A, but a ready-to-use plan still cannot be chosen until the manual and evidence for the actual set, area, airspace, power, trigger and turning interval exist. This height is not a permitted flying level, a preset or aircraft performance. Compare A/B with the same checklist, including the option of a ground walk-through/survey if resources are insufficient
Diagram description: use it to read the geometry and what is still missing; do not use it to command an aircraft. Open the full-size two-option diagram
A one-footprint coverage count for practice: place the first footprint flush with the lower/left edge, then shift the centre by the specified distance until the last edge covers the yard boundary. Using lines = ceil(max(0,300 − width)/line_spacing) + 1 and shots_per_line = ceil(max(0,200 − length)/photo_step) + 1 gives A = 6 x 9 = 54 images and B = 9 x 13 = 117 images . This formula only ensures each position is covered at least once, it is not a photogrammetry plan with enough overlap and tie coverage at the edges . It excludes turnaround, launch, buffer or refly, so this count cannot be used to cite time, power or a ready-to-fly grid
Check the residuals without making missing data disappear
Open survey-mapping-checkpoints.csv and the M01 set description has 8 synthetic rows: CHK-01-06 have complete residuals, CHK-07 has dx/dy but an empty dz in both versions, and GCP-01 is a control used for adjustment and must be excluded from accuracy. The reference uncertainty of 0.02 m is hypothetical metadata, not a real measurement; no type/confidence level is stated and there is no data on position distribution that could certify the area
dx,dy,dz = deliverable value - reference value in the same local axes and metres. v0/v1 are separately invented residual data variants , not results of flights or before/after processing runs, and there is no evidence that changing A to B improves the residuals. Use role=independent and used_in_adjustment=false and then compute only the values that are complete in each dimension:
RMSE_H = sqrt(sum(dx² + dy²) / n_H)
RMSE_Z = sqrt(sum(dz²) / n_Z)
bias_Z = sum(dz) / n_Z
Scroll the table horizontally to see all columns. When the table has keyboard focus, use the left or right arrow keys
| Result for the set | v0 | v1 |
|---|---|---|
| n_H: CHK-01–07 | 7 | 7 |
| RMSE_H (m) | 0.1458 | 0.0665 |
| n_Z: CHK-01–06 | 6 | 6 |
| RMSE_Z (m) | 0.2017 | 0.0327 |
| bias_Z (m) | +0.2000 | +0.0300 |
| Against the scenario's numerical criteria | H and Z do not pass | Passes only for the subset with complete values |
| Verdict on the whole delivered set | HOLD: the figures do not pass and CHK-07 lacks Z | HOLD: CHK-07 lacks Z |
Keep CHK-07 as an open item. Height/reference-system evidence and a traceable measurement method must be obtained before reassessment. Do not fill in 0 or discard it in order to report that the whole set passes. GCP-01, whose residual is only 0.001 m, is not included in n_H/n_Z because it was already used for adjustment, and the reference uncertainty is not subtracted from the RMSE without a model. This data only practises arithmetic and status judgement; the time, survey method, point positions, calibration and real reference for field work are still missing
Diagram description: different counts may be used in H/Z provided the reason and the missing parts are reported; do not use a subset figure to change the status of the whole set. Open the full-size independent-check diagram
B Beginner: explain the results and limitations in the brief
Before starting: for K, separate orthomosaic/DSM/DTM and GSD/accuracy; if you cannot yet, review deliverables and accuracy checking and then explain one example in one sentence each. For S, read the units and be able to multiply and divide; supplement with the image-capture plan and compute footprint A first. For E, separate hypothetical from real and image rights; review observation records and data handover . For C, keep the original version and accept feedback; review cross-checking within the team and then open the open-items record
Use the M01 beginner worksheet to write a one-page brief, explain the terms, compare A/B against the same criteria, and read the v0/v1 verdicts so another recipient can re-check them. Have the reviewer raise at least one comment and then correct it with a reason. Assess according to rubric M01
Scroll the table horizontally to see all columns. When the table has keyboard focus, use the left or right arrow keys
| ID / dimension | Target behaviour when given the M01 scenario | Activity and evidence | Criteria for each outcome |
|---|---|---|---|
| APP-M01-B-K01 / K | Explain the deliverables and separate GSD from accuracy | A brief with six term definitions and the scope of the DSM | All terms correct; does not use a DSM in place of a DTM or GSD in place of accuracy |
| APP-M01-B-S01 / S | Compare the two plans and read the check results according to the data | An A/B table with units, and a residual conclusion | GSD/footprint of both plans correct; states n_H=7 n_Z=6 and HOLD for both versions |
| APP-M01-B-E01 / E | Disclose missing data and image-rights conditions before proposing use | Limitations in the brief and the answer to a request to publish the images | Does not invent CHK-07 and does not certify the site; proposes a rights check/data reduction before sharing |
| APP-M01-B-C01 / C | Accept feedback, keep versions and follow up on the open items one has taken on | The brief before/after, the reviewer's comments and the open-items list | Every comment has an answer/reason, and CHK-07 has an owner and a next task |
O Practitioner/planner: make the plan and decide on acceptance checks
Before starting: for K, review receiving the brief and GCP/checkpoint , separating one control from the independent points. For S, review processing lab and field work and then try the formulas on two rows before the whole set. For E, review rights and handover and then write the extent of use of the results. For C, review the brief and roles and cross-checking and then name who does, who checks and who owns each open item. If this short check cannot be done, go back to Worksheet B and practise again
Use the M01 planner worksheet to make the seven-step plan, a register of people/resources/costs and ground options, compute A/B and the residuals by a method the reviewer can repeat, and write the HOLD criteria and a handover report that does not yet certify the whole set. Have the successor review the open items before correcting. Assess according to rubric M01
Scroll the table horizontally to see all columns. When the table has keyboard focus, use the left or right arrow keys
| ID / dimension | Target behaviour when given the M01 scenario | Activity and evidence | Criteria for each outcome |
|---|---|---|---|
| APP-M01-O-K01 / K | Explain the choice of set and the scope of the reference/independent points | Reasons for the aircraft type/sensor and the reference register | Has area/payload/support conditions; does not let RTK/PPK or GCP replace independent checking |
| APP-M01-O-S01 / S | Arrange the seven-step plan and assess whether data is complete in each dimension | The plan, people/resources, the A/B table and the formula report | Computed values match the answer key; keeps CHK-07, excludes GCP-01 and HOLDs the whole set |
| APP-M01-O-E01 / E | Deliver status according to the evidence and arrange access rights | A report to the recipient with the list of what is missing/rights/extent of use | Does not hide points that fail or are missing; does not send images of people/areas beyond the rights and necessity |
| APP-M01-O-C01 / C | Take responsibility for reviewing the plan and following up the hold conditions | The plan before/after, notes for the successor and owners of open items | The reviewer can follow the duties; every open item has an owner, the evidence to request and the condition for rechecking |
D Developer/tuner: define the interface and test plan
Before starting: for K, read the units, frame and requirements that can be checked from coordinates and requirement-to-test . For S, review integration and mass/balance and then write example inputs/outputs. For E, review the evidence report and handover rights , separating expected/actual. For C, review cross-checking and then keep the baseline and the rollback trigger. If reading the CSV/formulas is not yet fluent, do the calculation part in Worksheet O first
Use the M01 developer worksheet to make a requirement/interface/test plan only for adding a camera or changing how residuals enter QA, covering mass and CG, power, time/synchronisation, trigger, the lever arm between the position reference point and the camera, calibration and the manual of the actual set . State the units, axis directions, time, invalid/missing states and the owner of each interface. Do not enter hardware values that have no evidence
Lay out baseline/normal cases/wrong values/boundaries/before-after and rollback, such as a mismatched frame, different units, an empty dz, a control mixed in, a trigger time not tied to the capture time, or a calibration without a version. Ask which time log, reference report and calibration file are needed to fix it. Do not invent an empty dz. Separate expected results from actual ones, where the actual field for the hardware adjustment and the processing run is still not yet tested . Assess according to rubric M01
Scroll the table horizontally to see all columns. When the table has keyboard focus, use the left or right arrow keys
| ID / dimension | Target behaviour when given the M01 scenario | Activity and evidence | Criteria for each outcome |
|---|---|---|---|
| APP-M01-D-K01 / K | Explain the requirements and the interfaces that could produce wrong results | Requirements and interfaces with units/axes/time | Complete for mass/CG, power, time, trigger, lever arm, calibration, manual and evidence level |
| APP-M01-D-S01 / S | Tie the requirements to test cases and restore the baseline | A before-after/error/rollback test matrix | Checks missing Z, frame, unit, control, time and calibration; expected is correct and actual is reported as it is |
| APP-M01-D-E01 / E | Report unknowns and rights without inventing test results | Evidence status and conditions for export | Does not claim that hardware was adjusted or WebODM was run, does not fill in dz, and does not claim v1 resulted from Plan B |
| APP-M01-D-C01 / C | Keep the baseline, answer the reviewer and take responsibility for the rollback | The plan before/after, an issue log and the rollback | Has a trigger, an owner, the version to restore, a method of checking after restoring, and an answer to every comment |
Diagram description: K = knowledge, S = skills, E = ethics, C = character. E/C are checked from the reasoning and behaviour in recorded work, without attaching permanent personality labels. Open the full-size KSEC diagram
Check the work product, correct and resubmit, and record the evidence
Use the M01 rubric and model answers to check each of the 12 outcomes by code and record the result as has evidence per the criteria / needs more practice / no evidence yet with the reason in the shared learning record . Keep the work product before-after, the date, the reviewer, the criteria version and the replies to comments, then resubmit according to the corrections. E must show decisions about missing data and rights. C must show keeping versions, accepting feedback and following up open items. Do not pass someone merely because every field is filled in or the reading is finished

An AI-created illustration, not an image of a learner who passed assessment or a real acceptance result. Open the full-size review image
The code was added to curriculum-mapping.csv with the CLO/PLO still empty and the status pending_design used as starting data for later curriculum design. Worksheet results, a passing subset figure or a status of having finished reading do not certify field readiness require additional evidence on the team, the actual set, the area, airspace, reference, authorisations, rights and the relevant acceptance checks
Files, sources and scope
- Description and licence of the M01 set
- Worksheet B, beginner, Worksheet O, planner, Worksheet D, developer
- Synthetic checkpoint data and rubric with model answers
Primary sources reviewed on 11 October 2026: PIX4D is used for the definition of GSD; QGroundControl for the camera, overlap and flat-ground assumption; WebODM for control points/independent points and data-collection angles; CAAT 2022 for the structure of manuals and records within the scope stated. Links are placed near the text that uses them. These documents are not cited as certifying the training values or the learner's actual set. The formulas, residual data, example criteria and worksheets are newly composed work. This chapter has no original photographs, orthomosaic or DSM to download, and no evidence of trials with learners, equipment or a real site